|
Council Agenda - City of BurbankTuesday, September 11, 2007Agenda Item - 4 |
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
WATER UPDATE
Water Quality
Financial and Operations Update
BOU Water Production
Burbank Operable Unit (BOU) production was at 87.96% of plant capacity for July. This is an average flow rate (24/7) of 7,916 gallons per minute (gpm). Six of the eight water wells were available for service, with five wells providing the required flow. The pumps and motors of the two wells that are out of service have been repaired or replaced and installed. New power conductors, or wire, are being pulled through existing conduits for both wells. The pumps should be ready for service by the middle of August.
Environmental Protection Agency (EPA)
A signed design contract between ECO, the BOU O&M contractor, and MEGTEC, the design and construction contractor was in place December 15, 2006. A final design package was submitted to EPA at the end of July for the VPGAC carbon retention screen replacement project. EPA�s approval is the controlling feature in proceeding with this project. We are working to get an expedited review and approval from the EPA. MEGTEC will provide a final construction cost estimate when EPA approves the plans.
The EPA also requested a full scale test of utilizing virgin carbon in the VPGAC filter vessels and deleting on-site carbon regeneration. A test began on June 16th and will have to run a minimum of 60 days or until the carbon is exhausted. Lockheed Martin has agreed to bear the cost of all of this work. In the meantime, the MEGTEC design will be reviewed/approved so that a decision on the project alternative can be made as soon as possible. The testing will delay the start of the project until possibly October. Construction is projected to take 18 weeks and will likely be completed by the end of February 2008. The Treatment Plant will experience reduced operating capacity during project construction. There will be an increased need to purchase water from the Metropolitan Water District (MWD) during construction. However, the timing of the construction will now reduce the water volumes that will be purchased. These additional water purchases from MWD will significantly impact WCAC expenses and may result in the use of a significant portion of the WCAC balance.
San Fernando Basin Groundwater Credits
Burbank, Glendale and Los Angeles are discussing the issue of an over statement of Import Return Groundwater Credits in the San Fernando Basin (SFB). The discussion is centered on the calculation of the credits within the context of the 1979 Judgment that adjudicated the basin and is under the administration of the Upper Los Angeles River Area Watermaster. Burbank and Glendale are in disagreement with the Watermaster as to the proper application of the terms of the Judgment to resolve the imbalance of ground water credits. Los Angeles, Glendale and Burbank have continued to meet since January, and had tentatively reached an agreement with each other and the Watermaster. Glendale is additionally seeking an assurance of access to stored water for its GOU operation during the 10-year term of the agreement. Los Angeles will not concur. The parties are next scheduled to appear in Court on August 21, 2007 to discuss the status of the groundwater storage in the SFB.
Chromium Contamination in the Groundwater
Drinking water in Burbank does not exceed 5 parts per billion (ppb) chromium by direction of the City Council. This is achieved by blending the BOU produced water with MWD water to obtain the 5 ppb concentration. Current Federal and State Maximum Contaminant Limits (MCL) are 100 ppb and 50 ppb, respectively. Work has been underway for the last four years to develop a new limit for chromium. The work was done by the National Toxicology Program (NTP) within the EPA. Results of the study were released May 16, 2007. The study concluded that Chromium VI is a carcinogen when ingested. The study used high concentrations of chromium, the lowest being 5,000 ppb. The promulgation of a Public Health Goal (PHG) [none currently in place] and a new MCL are the next steps and will come from the California Department of Health Services. Water Industry speculation places the anticipated PHG between 3-30 ppb although some rumors place it much lower. A PHG lower than 5 ppb, if adopted by the City Council, would limit Burbank�s current operations and increase reliance on imported MWD water, or require additional treatment for removal of Chromium. Either alternative would significantly increase Burbank�s water costs and strain the water supply.
Water Supply and Conservation
Given the current drought conditions in the Colorado River Basin, this year�s minimal rainfall in Southern California, and the �temporary� shut down of the State Water Project (SWP) export pumps, it was deemed prudent to intensify Burbank�s message of water conservation in June. Continued uncertainty through July about the allowable long term capacity of the SWP pumps has led MWD to call for conservation at a voluntary 10% level. Although, Burbank is currently well positioned for water resources to support regular use for this year, it demonstrates good stewardship and furthers public education and understanding of a real potential for a long term need for conservation until the pumping capacity limitations on the SWP are resolved. The resolution may take ten years or longer. In the interim, MWD has projected that cutbacks of as much as 30% of imported water may be necessary. This will require a new approach in our thinking about the customary use and value of water.
Existing groundwater resources and the use of recycled water have offset a prior total dependence on water imported and treated by the Metropolitan Water district (MWD). Roughly half of Burbank�s projected potable water use will be provided from MWD as treated water. Past voluntary efforts in Burbank during drought conditions have yielded as much as a 20% reduction. Burbank has also shifted potable use to the recycled water system as the recycled system has been developed. Those parks, golf courses and businesses that utilize recycled water will not be affected by any conservation measures aimed at reduced landscape irrigation.
Continued efforts to install water saving home and business fixtures, irrigation systems and California friendly gardens, along with the City�s plans to expand its use of recycled water through the approval and implementation of a new recycled water master plan, will help position the community in terms of efficiency and our ability to withstand prolonged drought conditions. The Council may wish to consider actions like ordinances to require retrofitting or upgrading of fixtures upon the sale of property or drought operations ordinances which might provide for enforcement of operating practices during a period of extended drought (both of these are included in the Sustainability Goals for consideration by Council).
Capital Projects
Legislative Update
Refer to the attached legislative reports.
ELECTRIC UPDATE
Safety
So far during Fiscal Year 2007/08, we have had zero lost time incidents.
Electric Reliability
There were two, 4 kV feeder outages and two, 12kV feeder outages in July. These outages interrupted service to 1,967 customers for a total of 253 minutes.
Despite the power outages in July, BWP�s overall reliability continues to be strong. As of July 31, 2007, the system-wide average is 0.0386 outages per year, compared to an industry average of 1.2 outages per year. The average service availability is 99.9957%, exceeding the City goal of 99.99%. The average outage length is 49.45 minutes, compared with the industry average of 80 minutes.
The following table shows the system-wide reliability statistics for Fiscal Year 2007-08 through July 31, 2007, as compared to the same time period for Fiscal Year 2006-07:
Financial and Operations Update
Local Generation Operations Update
Unit Status
July 2007 Unit Data
Magnolia Operations Update
Workforce Safety Statistics:
Performance Information:
Actions Taken by Operating Agent:
The Plant went down on July 3, when the fuel gas compressor (FGC-B) tripped on high vibration because a bolt on the north compressor cylinder broke. This happened while the motor for the spare compressor (FGC-A) was in the shop, so there was no functional spare. Plant operation was restored the next day on July 4, after the gas compressor (FGC-B) was repaired.
The Plant went down on July 27, when the fuel gas compressor (FGC-A) tripped because of a loose wire on the emergency stop switch. The combustion turbine tripped on high exhaust temperature spread before the automatic switchover to the spare fuel gas compressor was accomplished. A plant restart was attempted after a few minutes, but the HRH (hot reheat steam) bypass valve was stuck closed. It was necessary to cool the unit down until the HRH bypass valve would open. Plant operation was restored on July 30.
During startup on July 30, the combustion turbine tripped on high exhaust temperature spread. Plant operation was restored on July 31. The high temperature spread on the combustion turbine exhaust may have been caused by a flame-out so GE is reviewing the data remotely to determine the cause.
Summarized below are MPP estimated costs for 2006/07 Fiscal Year compared to budget:
Renewable Energy Update
Utah Wind Development
Work on the power sales agreement between SCPPA and its members was finalized during the past month. Staff expects to seek approval to proceed with this project from the BWP Board in early August, and from Council later that month. Burbank has a 10 MW interest in this resource.
Pacific Northwest Wind Development
During the month, negotiations continued with the developer of a wind facility located in the Pacific Northwest. It is expected that a power sales agreement will be finalized during August. Burbank has a 10 to 20 MW interest in this resource.
Imperial County Geothermal Development
SCPPA continues with the preliminary planning work on a geothermal facility in Imperial County. The initial review of the geothermal prospects are of potential interest to SCPPA. The next step in the planning process is do some exploratory well drilling at a half dozen locations to determine the profile of the subsurface temperatures of the resource. It is expected that this work will begin in the early fall. The in-service date of this project is currently anticipated to be in late 2011, or early 2012. Nine (9) MW in an initial phase would supply 6% of BWP energy requirements. Energy would be delivered to BWP via the proposed Greenpath Transmission Project for which an update can be found below.
Greenpath Transmission Project
Planning work continued on this project. Generally, the route will connect a new electrical substation in Hesperia to the Devers II Substation which will be built near Palm Springs. Specific activity focused on identifying the potential corridors that will be studied in order to determine the ultimate route for the transmission line. The goal is to find the route that will result in the least impacts on the environment, critical wilderness areas, and existing urban development. The environmental investigations related to the proposed project must meet the requirements of both State and Federal law. The process is very lengthy and public and involves preparation of an Environmental Impart Report (EIR) mandated by the California Environmental Quality Act (CEQA) which will have LADWP acting as the lead agency, and an Environmental Impact Statement (EIS) as mandated by the U.S. National Environmental Protection Act, which the Bureau of Land Management and the U.S. Forest Service will be the Federal agencies jointly acting as lead agencies.
The project�s anticipated in-service date is late 2010, or early 2011. Current plans are for 1200 MW transfer capability. However, ultimately this may be increased to 1600 MW.
SCADA/EMS
BWP engineering staff is currently working with Siemens New Energy on an upgrade to the existing New Energy Scheduling System to improve participant use.
Station RTUs are being upgraded to control the Sequence of Events (SOE) to an accuracy of 1 milli-second. This is done by adding a GPS clock and a SOE board to each RTU. Engineering work is in process to link SCADA data to the Responder System.
Telecom
Engineering developed the following fiber optic service proposals:
Engineering released two (2) fiber optic service jobs related to the Olive Avenue Underground Project.
BWP Field personnel completed two (2) fiber optic service jobs related to the Olive Avenue Underground Project. These jobs re-routed fiber links affected by the project:
BWP Facility Improvements
Implement Automatic Reclosing of Distribution Circuits
Often, an object causes a short circuit on an overhead power line for only an instant (technical term: transient fault), and does not damage the line. For example, a branch may fall between two conductors, touching them only briefly; or a kite tail may instantly vaporize as soon as it touches two conductors. The utility industry has responded to these situations by using reclosers, which closes a line back in very soon after it has been short circuited. If the cause of the short circuit is no longer present, the line stays in service; if the cause is still present, the line relays out soon enough to avoid damage to the line.
Re-closing is especially important for BWP's six, mostly-overhead 12,470-volt (12 kV) circuits, which serve two to three times as many customers than the older, 4,160-volt feeders. BWP will add the re-closing feature to two, 12 kV distribution circuits (Keystone-6, Keystone-13) before September 16, 2007 and to 4 circuits (Hollywood Way-4, 5, 6, and 7) before January 2008. BWP is finalizing its reclosing procedures, which will assure that reclosing does not endanger electrical workers who may be working on these lines. BWP will meet and share the new procedures with the International Brotherhood of Electrical Workers (IBEW) before implementing.
4,160-Volt Distribution System- Impacts of heat wave and follow up action plan
After the July 2006 heat wave, the Energy Control Center (ECC) initially reported 32 distribution circuits showing overloads. BWP carefully reviewed the loading of those circuits and identified 12 distribution circuits that needed reconductoring with larger lines that can safely carry heavier currents:
As of June 30, crews reconductored 30 miles of overhead conductor and approximately 2 miles of underground cable. In July 2007, all major feeder reconductoring jobs related to the July 2006 heat wave were completed. Only the lateral overhead conductors of Victory-14 and Town-4 will remain and crews will continue to work on those along with other planned 12 kV conversion jobs.
The reconductoring work was not a part of the Fiscal Year 2006/07 CIP Budget as the need for it did not become apparent until after the July 2006 heat wave. When completed, this work will have cost $1.7 million ($1.1 million for labor/overhead and $600,000 for conductor, cable and other materials). The impact on the Fiscal Year 2006/07 CIP Budget led to delays in three budgeted capital projects: Olive-Valley No. 2, Replacement Burbank Station, and Olive Avenue Underground Utility District 1.
Substation power transformers serve a neighborhood, or a very large customer like a major studio. Even during the 2006 heat wave, all substation transformers were loaded well under their rated capacity because every substation has two or three substation transformers. If one of the substation transformers should fail during a heat wave, the remaining transformer(s) will be able to handle the other transformer�s load as well as its own with minimal overload. Nevertheless, BWP believes it is prudent to assess the remaining useful life of its substation transformers so that it can replace them well in advance of a crisis situation. The average age of those station transformers is 45 years, with some as old as 66 years.
Doble Engineering Company is assessing 30 critical transformers, and are currently making visual inspections and analyzing available records. Analysis and review of maintenance records and past loading history of station transformers continued through July. (Other critical transformers will be reviewed next fiscal year.)
BWP Administration Building - Phase III Interior Remodel
Icon West, Inc. completed construction work in the basement-level of the Administration Building. Construction work is nearing completion on the first floor (east wing) and second floor (west wing). Work is progressing on the second floor (east wing) and demolition work is complete on the third floor. The project completion date for the entire building remodel is January 2008.
BWP Service Center and Warehouse Project
BWP is negotiating a contract with McCormick Construction Company guided by the bridging documents by Kennard Design Group. If BWP and McCormick agree on a first lump sum price, and terms and conditions, it would be scheduled for City Council approval by August 31, 2007. If not, BWP is prepared to re-bid the work. Construction is scheduled to begin in January 2008, with a target completion of July 2008.
The next phase will demolish the existing Warehouse, the Line Section field offices, and the covered storage and parking. This area will be converted to employee vehicle parking. The next phase will also demolish the existing Water Maintenance Building along with the Guard House, and install landscaping and additional employee parking. A new Security Office of approximately 600 square feet will be constructed on Lake St. at the intersection of Palm Ave. that will control ingress/egress to the entire BWP campus. A vehicle wash rack will also be added. Completion of the aforementioned phases is anticipated for January 2009. The final phase of the project constructs a replacement Burbank Substation with a state-of-the-art GIS substation. The GIS substation will be built at the southwest corner of the campus on a footprint one-third the size of the existing Burbank Substation. All equipment will be removed from the existing substation, the site will be scraped and the area converted into a courtyard.
Security Wall Construction
McClean & Schultz, Principal Architect, completed a structural review including engineering signatures/stamp on the drawings prepared by Bibb. Once the final construction documents are completed, a bid package will be assembled and submitted to Purchasing for the competitive bid process to hire a contractor. Work is anticipated to begin January 2008, and be completed in March 2008.
Communication Shop Relocation
Work has begun to provide a new home for the Communication Shop. McLean & Schultz completed and submitted the final construction documents and technical specification package. Remediation and removal work has been completed. Icon West will begin tenant improvement work on the Communication Shop in August 2007. The anticipated completion date for this work is December 2007. Communication Shop staff can then be relocated, allowing for the construction of the Replacement Service Center/Warehouse in January 2008.
Electrical Distribution
Construct a New Olive-Valley #2 Line
Olive Station Portion: Breakers are on the new equipment pads; disconnect switches have been mounted on the supporting structures. We need to build the structures and devices to terminate new underground cable from the newly installed duct system which is underway along Olive Ave. Engineering for relays and panel work is currently underway and will be issued to the field crews.
Olive Underground Portion: Duct and maintenance vault construction is underway along Olive Ave. and completed from the Olive and Lake intersection to the Olive and Victory intersection, and north and south of the intersection to the new riser pole. Duct work is 90% complete in the block between Lake St. and the west edge of the Olive Ave. Bridge. Work will be completed by August 17, and the final street paving will be scheduled for sometime in late August or early September.
North-South Victory Portion: This work has not yet begun. The work calls for new insulators and reconductoring, but not pole replacement. This project was delayed to allocate field resources to complete the reconductoring jobs originated as a result of the July 2006 heat wave.
Five Points Underground Portion: Ducts and maintenance vaults installed at the time of the Five Points project.
East-West Victory Portion: Construction of the overhead portion of this line along Victory Blvd., from the Costco area to Victory Blvd. and Fairview St. will include the replacement of 30 poles, upgrading 3,000 circuit feet of overhead conductor, adding new polymer insulators and changing the insulators from porcelain to polymer. The poles and other material have been ordered, and locations of the new proposed poles are marked in the field. Construction of the overhead has been delayed to Fall 2007 in order to utilize the field crews on reconductoring jobs.
Valley Station Portion: The consultant, ORSA, completed the design for pads and underground power conduits for the extension of the ring bus at the Valley Switching Station. Bock Company completed the duct work inside the substation and through Ralph Foy Park. They also completed all duct work required on Victory Blvd. up to Fairview and to the new riser pole. The final design for ground grid and equipment pads was completed and issued for construction. All equipment pads, control/communication conduit work along with the ground grid work in the extended ring-bus area is completed. All breakers and disconnect switches are set on the pads and structures. Most of the bus work is finished and the remaining bus work was completed June 30, 2007. The remaining ground-grid, control/communication wiring work, and relay panel work is estimated to be completed by March 2008.
Replacement Burbank Station Project.
A contract was awarded to ABB Inc. in the amount of $17,247,260. All major pieces of equipment with a long lead time have been ordered. Construction of the duct system on the BWP campus started on April 23, 2007 and was completed by June 30, 2007, except for one maintenance vault to be installed this fall. Duct work outside the BWP campus along Lake St. from the security gate to Magnolia Blvd., along Magnolia Blvd from Lake to Moss St. and the alley south of Magnolia Blvd. between Lake and Victory will start during the summer of 2007. All duct work will be completed by December 31, 2007, including all station getaways at Lake St. between Olive Ave. and Orange Grove Ave. The foundation and equipment pad construction will start on August 15, 2007 and will continue until December 2007. Major equipment delivery will take place in December 2007 and January 2008. The Station will be partially energized by June 2008. Most of the 34,500-volt network will be transferred to the new station by June 30, 2009. All 4,160-volt load that is directly served from the Burbank Station will be transferred and de-energized, all station equipment physically removed, and the station demolished by June 30, 2010.
Compliance with NBC Master Plan - Planned Development 96-1
BWP staff provided comments to the Community Development Department regarding the compliance with Planned Development 96-1, expanding the parking under LADWP�s 230 kV high voltage lines near NBC, and the method of service for M. David Paul Development on the Catalina property. Providing electric service for this development involved an extension of the 34,500-volt line (ducts and cable) from Willow St. along Fredrick St. to Alameda Ave., and along Alameda Ave. from Fredrick St. to Naomi St. This work was completed in March 2007.
The new 34,500-volt line position at Naomi Station as well as a small amount of work at Capon Switching Station was completed in March 2007.
On the Catalina site, two padmount switches and four padmount transformers will be required to transform power to utilization voltage for the parking structure and both office buildings. Under the current BWP Rules and Regulations, M. David Paul will pay 100 percent of the cost of the work directly related to its service as aid-in-construction charges, and will also reimburse BWP its prorated share of system improvements completed since July 2001. On January 26, 2007, Krismar Construction Company, on behalf of M. David Paul, paid $1.2 million as a reimbursement for the system improvement for Phase-1, and paid $300,000 as a first installment of the direct cost of service. Krismar Construction paid the second installment of $300,000 on April 10, 2007, and paid the remaining $455,000 on July 11, 2007. Phase-2 of the project is two to three years away.
Reliability of the Golden State Distributing Station
In most of BWP�s substations, BWP can restore power by making use of a direct connection to the station transfer bus, or by transferring load to other stations. These options are not available at the Golden State Substation, which experienced switchgear problems in 2005. Working with its engineering consultant, Power Engineers Inc., BWP has found a way to make a direct connection between Golden State�s transfer bus and the power transformers, while also adding a substation capacitor bank. The City Council approved this work at its March 13, 2007 meeting. BWP has negotiated the price, terms and conditions of the agreement with ABB Inc. During negotiations ABB suggested we add disconnect switches to the direct connection in order to shorten the customer restoration time. A purchase order was issued on June 6, 2007. ABB has ordered a capacitor bank, circuit breakers, disconnect switches and other long lead items. The preliminary design is in progress and the construction is expected to start in late Fall 2007 or early Winter 2008, and be completed before May 1, 2008.
12,470-Volt Distribution System
The construction work to rebuild and energize to 12 KV the 4 kV feeder areas A-8, A-96, and A-97 is nearly done. All customer stations have been rebuilt to 12 kV. This will allow conversion of this area to 12 kV service from the new Hollywood Way Distributing Station (Feeders HW-4 and HW-6). It goes along with BWP�s plan to transfer load to new state-of-the- art substations like Hollywood Way, and will eliminate aging substations like the Alameda Substation. The residential portion of Feeder A-8 was converted to HW-4 on June 6, and the commercial portion, including Vons grocery store at Pass Ave. and Oak St., was converted on July 1, 2007. The first portion of Feeder A-96, south of Verdugo Ave. and west of the Warner Ranch to the City�s boundary, was energized to 12 kV on June 13. The remaining area, bound by Verdugo Ave., Clark Ave., Pass Ave. and Clybourn St., was converted on July 17. Approximately half of the Feeder A-97 load bound by the area of Hollywood Way, Clark Ave. Pass Ave. and Verdugo Ave. will be energized to 12 kV on August 14, and will be served by HW-6. The remaining half of the load east of Hollywood Way between Verdugo and Oak Sts. will be transferred to Alameda-9 in the end of October 2007. After completion of this work, Alameda Feeders A-96 and A-97 will be physically removed from the Alameda Distributing Station and the Feeder A-98 load will be transferred to the vacant position of Feeder A-8. This work is also required as a part of the Caltrans SR-134 project and will allow the positions of A-96, A-97 and A-98 feeders in the Alameda Station to be removed as well as the Transformer Bank A-3 serving them.
Progress continues on single pole replacements. Rebuilding deteriorated pole lines will start as soon as the reconductoring work is complete.
The Keystone and Golden State Distributing Stations were included in the under-frequency load shedding scheme to provide better capability to automatically shed load and balance load with generation. This addition will help to stabilize and restore the system much faster in the event we lose a big generation source such as the tie with LADWP or MPP.
Customer Transformer Stations
In July 2007, Engineering responded to 11 written requests for review and comments from the Community Development Department and other City Departments. New business, and a strong residential real estate market, has created a demand for new customer stations.
In July, Engineering designed 3 replacements of deteriorated padmount transformers. One vault-type customer station has been removed and will be replaced by padmount switch/padmount transformer services. This design will contribute to the expansion of the underground loop system.
Project Lightspeed
Engineering has processed 147 submittals from the AT&T Project Lightspeed. The crews have energized 120 services completed by AT&T contractors.
Undergrounding
Underground Utility District No. 1: The City Council approved the establishment of the first Underground Utility District within the City of Burbank for Olive Ave. between Victory and the I-5 overpass. Construction started in early April and is progressing very well. Except for final paving, J Fletcher Creamer has completed the underground conduit work at Olive Ave. between Victory Blvd. and Lake St., and Lake St. between Olive Ave. and Orange Grove Ave., and along Orange Grove Ave. They also completed underground conduit work in the alley north of Olive Ave. and east of Victory Blvd. behind the 7-11 store. They installed maintenance vaults and conduit at Victory Blvd., both north and south of the Olive Ave. intersection, and Olive Ave. between the I-5 Bridge and Victory Blvd. In the mean time, the Okonite Company has delivered all of the 69,000-volt cable to the BWP campus. The duct system for the 69,000-volt lines is ninety-eight percent complete and the cable installation has started. Undergrounding for Phase-1 including the cable installation, is estimated to be complete by October 31, 2007 and removal of the overhead poles and wires by November 30, 2007.
Caltrans: BWP Engineering completed two projects related to Caltrans. One project involves the Alameda, Hollywood Way and Pass Ave. bridge widening on the SR-134, and a new on-ramp at Hollywood Way. The second project involves the I-5 freeway, Empire Exchange, and San Fernando Realignment. Caltrans awarded the contract for the SR-134 Project and requested a Utility Agreement be approved. The City Council approved the agreement on March 13, 2007, and extended the contract with Bock Company for the duct work. Bock Company started work at Riverside Dr., between Olive Ave. and Hollywood Way, and modified the communication pull box in front of the Alameda Distributing Station to allow space for adding an east bound right hand lane between Hollywood Way and the proposed on-ramp. Bock Company will continue to support BWP as needed to meet the schedule of the Caltrans Project. As of June 8, 2007 Bock Company has completed most of the work along Riverside Dr. between Olive Ave. and Hollywood Way. Caltrans has started widening the north side of the Alameda Avenue Bridge over SR-134. After the August 16, 2007 meeting with Caltrans, Bock Company will start installing electrical ducts in the bridge and work towards the intersection of Alameda Ave. and Hollywood Way. On the north side of the Alameda Bridge all cable installation and transfer of load to the new system is expected some time in November 2007, depending upon the completion of the duct work in the bridge and the intersection.
Meters
A total of 244 remote read meters were installed in July.
Streetlighting System
In July, Engineering designed and issued to Operations two individual streetlight installations and a new streetlight system around the perimeter of the Marriott Residence Inn. Engineering is working with Public Works and the Traffic Signal Division on new street/traffic improvement projects (several Burbank Blvd. intersections, Main/Victory, Third/Verdugo, Hollywood Way/Winona, and Hollywood Way/Thornton).
RED:BL:FCF:WOM:GLS:JLF:ph H:OPERATIONS REPORTS\SEPTEMBER OPERATIONS REPORT
Attachment
|