Council Agenda - City of BurbankTuesday, March 13, 2007Agenda Item - 6 |
|
|||||||||||||
|
|||||||||||||
PURPOSE
Staff requests that the Burbank City Council (Council):
Both actions are necessary to begin relocating the electrical facilities by May 1, 2007, so that the work can be completed by April 30, 2009.
BACKGROUND
The SR-134 Ramp Project has become active again. Caltrans intends to build the westbound on ramp to SR-134, near the intersection of Hollywood Way and Alameda Avenue. Several years ago, Caltrans had relocated its westbound off ramp a hundred feet or so to the east. Council may recall that BWP had to abandon its existing Hollywood Way Station and build a new one to the east. Both relocations enabled Caltrans to secure the routing for the initial leg of the westbound on ramp.
At present, Caltrans has selected the Santa Fe Spring-based Griffith Company to build the westbound on ramp at an estimated cost of $29.5 million. Caltrans is expected to issue a purchase order in March and will probably begin construction by FY 2007/08, some three-and-a-half months from the date of this report.
To accommodate the westbound on ramp, BWP will need to relocate its electrical underground facilities. The SR-134 Ramp Project requires BWP to relocate its electrical underground facilities at certain locations:
An overhead pole anchor at Screenland Drive on the north side of SR-134 also needs to be relocated.
Caltrans has set aside $2,989,285 for this work, along with a 25% contingency. BWP has reviewed the design and estimated costs for the underground work with ORSA Consulting Engineers, Inc. (ORSA) and Dorado Company (Dorado), both of whom consult for the Community Development Department (CDD). All are comfortable that Caltrans has set aside sufficient funds.
Before undergrounding work can proceed, the Council will need to authorize BWP to enter into a Utility Agreement with Caltrans. The attached Utility Agreement would authorize the relocation of BWP�s electrical facilities, per the plans and specifications prepared by ORSA and approved by BWP and Caltrans. The Utility Agreement would also enable Caltrans to reimburse the City for project expenditures and would maintain prior rights for any future relocation.
Before undergrounding work can proceed, the Council will also need to authorize appropriation of the $2,989,285 base amount, plus the 25% contingency of $747,321, for a total amount of $3,736,606. The appropriation would be from CDD-Planning/Transportation Unappropriated Account No.127.ND000.30004.0000.00000 to CDD-Planning/Transportation Project Account No. 127.CD33A.70002.17615. CDD�Planning/Transportation would meet the cash flow requirements by authorizing BWP to charge up to $3,736,606 to its account and Caltrans will reimburse CDD as the project progresses.
Staff�s challenge is to select a contractor who will do the underground duct work at a competitive price and begin by May 2007. For planning purposes, it is useful to divide the undergrounding work into three components:
BWP�s underground crew will pull and splice the cable, with other BWP crews assisting as necessary with the removal of abandoned circuits. BWP can administratively extend its existing contract with Okonite Company by one year in order to assure the timely procurement of the underground cable.
Staff�s challenge was to find a timely way to engage a contractor for the ductwork and maintenance vaults, particularly for the difficult work within the bridges. Caltrans is expected to issue a Purchase Order in March and will probably begin construction by FY 2007/08. If Caltrans were to begin its work on the Alameda Bridge as early as July, then BWP�s underground contractor would need to do preparatory work in May.
Staff�s solution is to engage Bock Company. Under Bid Schedule 1137, and effective May 1, 2003, the BWP Board had approved a time-and-materials contract with Bock for an amount not-to-exceed $600,000. The contract had a price adjustment clause:
The contract also has a renewal clause allowing contract renewal on a year-to-year basis for up to three years beyond the first year. Owing to Bock�s excellent track record, BWP has exercised this clause for all three additional years, extending the contract to April 30, 2007.
Before BWP can engage Bock beyond April 30, 2007, the Council needs to authorize a two year extension. BWP has no administrative authority to extend the contract with Bock beyond four years from May 1, 2003. Any further extension of the contract requires Council approval.
ANALYSIS
The underground duct and maintenance vault work for the SR-134 Ramp Project will cost between $782,500 and $980,000. The $2,989,285 base amount breaks down as follows:
If the 25% contingency is applied across the board, then the cost of the duct work between May 1, 2007 and April 30, 2008 would be 125% of $782,500, or $980,000 in round figures.
For underground jobs, BWP has engaged private contractors on a time-and-material basis as well as a lump-sum basis. Since the early 1980�s, BWP has been using private contractors to install ducts and maintenance vaults for its electrical underground system. BWP�s usual practice is as follows:
From time to time, BWP has engaged Bock on both a time-and-materials and a lump-sum basis with a not-to-exceed cap, according to the nature of the job being bid and Bock�s success in presenting the lowest responsible bid.
Given the cost uncertainties, the underground substructure work for the SR-134 Ramp Project is best pursued on a time-and-materials basis. As mentioned earlier, underground substructure work could begin as early as May, although Caltrans has not yet issued a firm construction schedule. Erring on the side of quickness, one could argue that going on a time-and-material-basis, especially when seeking competitive bids, is a better than the lump sum approach. However, a more compelling reason is the high cost uncertainty in spite of well-defined job sites.
In the course of doing its earlier work on the SR-134 Ramp Project, Caltrans initiated a number of changes during the construction phase as various unexpected field conditions presented themselves. The work that Caltrans plans to do in the current phase carries a 25% cost contingency factor, suggesting that Caltrans is making a considerable allowance for more unexpected field conditions. Staff therefore believes that a time-and-materials approach is more prudent than a lump sum approach, in spite of the high dollar value of the work.
Given the current bidding climate, the underground substructure work for the SR-134 Ramp Project is best pursued on a sole-source basis if a suitable contractor can be identified. Between March and May, staff could go out for competitive bids on a time-and-material basis, though the schedule would be tight. However, BWP has recently had difficulty attracting enough bids; only two contractors responded to the Olive Avenue Utility Underground District work with very high bids, in spite of BWP�s extensive outreach efforts. A re-bid attracted one bid response, fortunately one much closer to the engineer�s estimate. Given the continued tightness of the construction market, there is a strong chance that even bidding on a time-and-material basis would be longer and less satisfactory than in the past.
Bock is a very suitable contractor. Bock has an excellent track record with BWP with regard to both cost and performance:
For these reasons, staff believes it unlikely that a time-and-material competitive bid process, even if swifter than expected, would yield a cost or schedule result superior to extending the existing contract with Bock.
If Bock is to do the work for the SR-134 Ramp project, the contract extension should also allow for BWP�s other underground substructure work. In FY 2007/08, BWP expects to spend $750,000 on electric underground substructure work. (This is higher than its recent pace of $600,000 per year because of more aggressive maintenance vault repair as well as an underground project along Hollywood Way.) Of this proposed budgeted amount, $600,000 is for various system improvement projects, $100,000 is for customer-funded projects, and $50,000 is for fiber optic projects.
The arguments favoring the extension of the Bock contract for the SR-134 Ramp Project also favor extending the contract for BWP�s other work. The contract extension would be for a total of $1,730,000, of which $980,000 is for SR-134 (including contingency) and $750,000 is for BWP�s other projects.
BWP complied with bargaining group MOUs. During the bidding process in 2003, BWP met and conferred with BCEA (per Article XIA.1of the BCEA MOU), the IBEW (per Section E.5 of the IBEW MOU) and BMA (per Article XI of the BMA MOU). No labor union had any objection to proceeding with a private contractor install electric underground ducts and maintenance vaults and related improvements. The work contemplated under the contract extension is of the same nature.
FISCAL IMPACT STATEMENT
The fiscal impact is positive. Extending the contract with Bock offers the best chance of controlling initial costs and meeting the schedule for the SR-134 Ramp project. Because the contract is on a time-and-materials basis, the Council neither obligates itself to spend the full not-to-exceed amount nor has to commit to BWP proposed capital improvement spending levels for underground substructure work.
Staff proposes to fund this utility construction work via the Fund 127 Development Impact Fee. If approved by the City Council, $3,736,606 from account 127.ND000.30004.0000.000000 Unappropriated Development Impact Fees to project account 127.CD33A.70002.0000.17615. CDD�Planning/Transportation would meet the cash flow requirements by authorizing BWP to charge up to $3,736,606 to its account and Caltrans will reimburse CDD as the project progresses.
CONCLUSION
Based on all foregoing reasons stated above, such as the urgency of the construction schedule and the current construction market, staff believes that a finding can be made under Charter Section 54 that it is in the best interest of the City to waive formal bidding and extend the contract with Bock Company for one more year.
RECOMMENDATION
Staff recommends that the Burbank City Council (Council) adopt a Resolution that:
If the Council concurs, the appropriate action would be the motions to adopt Resolutions entitled:
1. A RESOLUTION OF THE COUNCIL OF THE CITY OF BURBANK AMENDING THE FISCAL YEAR 2006-2007 ANNUAL BUDGET AND APPROVING AND AUTHORIZING EXECUTION OF ELECTRIC UTILITY AGREEMENT NO. 7UA-11432 BETWEEN THE CITY OF BURBANK AND THE STATE OF CALIFORNIA FOR THE SR-134 RAMP PROJECT
2. A RESOLUTION OF THE COUNCIL OF THE CITY OF BURBANK APPROVING AN EXTENSION OF THE CONTRACT WITH BOCK COMPANY FOR TWO YEARS FOR THE CONSTRUCTION OF UNDERGROUND CONDUIT SYSTEMS AND RELATED IMPROVEMENTS UNDER BID SCHEDULE NO. 1137 IN AN AMOUNT NOT-TO-EXCEED $1,730,000 FOR THE FIRST YEAR AND $1,250,000 FOR THE SECOND YEAR AND AUTHORIZING EXECUTION OF SAID CONTRACT EXTENSION.
RED:GLS:DDB:psm
Attachment
c: R. Morillo P. Herman L. Villegas B. Liu G. Hermann Amended Resolution Title
A RESOLUTION OF THE COUNCIL OF THE CITY OF BURBANK APPROVING AN EXTENSION OF THE CONTRACT WITH BOCK COMPANY FOR TWO YEARS FOR THE CONSTRUCTION OF UNDERGROUND CONDUITS SYSTEMS AND RELATED IMPROVEMENTS UNDER BID SCHEDULE NO. 1137 IN AN AMOUNT NOT-TO-EXCEED $1,730,000 FOR THE FIRST YEAR AND $1,250,000 FOR THE SECOND YEAR AND AUTHORIZING EXECUTION OF SAID CONTRACT EXTENSION.
|