|
Council Agenda - City of BurbankTuesday, January 23, 2007Agenda Item - 5 |
|
|||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||
PURPOSE
Staff requests that the Burbank City Council (Council) adopt a Resolution approving plans and specifications, and awarding a contract to J. Fletcher Creamer and Sons to install a conduit system within Olive Avenue Underground Utility District No. 1 (UUD#1) for $1,773,910 (Bid Schedule 1225).
Of this amount, $1,288,538 is Burbank Water and Power�s (BWP�s) share, with the remaining $485,372 divided among four communications utilities that must also underground their lines within UUD#1. Staff also requests that Council approve this cost allocation, as detailed in Table 1 of this staff report, and specifying that the four communications utilities must fully reimburse BWP by July 31, 2007.
BACKGROUND
On June 20, 2006, Council established Olive Avenue Underground Utility District 1 (Resolution 27,255), in which all utilities, not just those of the City, underground their lines at their expense. One of the first steps was to go out to bid for the conduit and maintenance vault work along Olive Avenue, and along the portion of Lake Street in front of the Replacement Burbank Station. (For background information on UUD#1, please see the attached staff report dated June 20, 2006, and the associated Resolution 27,255.)
Staff had prepared Bid Schedule 1220 for the installation of the conduit system and maintenance vaults, but received bids that approached twice the engineer�s estimate of $2,000,000. Working with other utilities also having to underground their facilities along Olive Avenue (AT&T, Charter Communications, and Verizon), BWP had completed detailed drawings and specifications for the underground work, calling for a common trench wherever possible. The Burbank Leader had advertised Bid Schedule 1220 on July 19 and July 22, 2006; and BWP
had held a pre-bid meeting on August 9, 2006. Although representatives from nine companies had attended the pre-bid meeting and job walk, only two had submitted bids at the bid opening on September 5, 2006.
Hermann Weissker Company had bid $3.5 million, 175% of the engineer�s estimate; and Henkles & McCoy had bid $3.9 million, 195% of the engineer�s estimate.
The City rejected both bids under Bid Schedule 1220 and solicited new bids under Bid Schedule 1225. On September 15, 2006, at staff�s request, the City Manager rejected both bids and authorized staff to solicit new bids.
ANALYSIS
Staff�s first response was to shift the work along Lake Street to the design-builder of the Replacement Burbank Station. Most of the circuits entering and leaving the Replacement Burbank Station will go through one or more maintenance vaults along Lake Street, near the intersection with Olive Avenue. Shifting the installation of these vaults, and related conduit work, to the design-builder provided two advantages:
The engineer�s estimate for the remaining portion of the work, the conduits and vaults along Olive Avenue, is $1,580,000 ($2,000,000 less $420,000).
Staff also made changes in its contractor requirements that would attract lower bids. With the approval of Public Works, more of the contractor�s working hours would occur during the day rather than the night. Bidders could estimate repaving costs based on the actual location of the trenching. And, staff increased project completion time from 115 days to 135 days.
Abovenet�s participation increased the engineer�s estimate by $30,000, from $1,580,000 to $1,610,000. As staff was preparing Bid Schedule 1225, an additional communications company, Abovenet, planned to install lines along Olive Avenue between Flower Street and Lake Street. BWP and the other communication companies granted Abovenet�s request to place their lines in the common trench.
Bid Schedule 1225 attracted a bid that was 10.2% above engineer�s estimate of $1,610,000. BWP staff held a pre-bid meeting on October 31, 2006 and approached three major construction companies (Pouk and Steinle, PAR Electric, and Contra Costa Electric) which had been proposed subcontractors to the Replacement Burbank Station Project (RFP 1216). In spite of these outreach efforts, only J. Fletcher Creamer submitted a bid at the December 5, 2006 bid opening. However, at $1,773,910 this bid was considerably closer to the engineer�s estimate than those submitted under Bid Schedule 1220: 10.2% over versus 75% over and 95% over.
In comparison to the engineer�s estimate for the total work, $2,030,000 (which includes the $30,000 from the Abovenet addition), staff has been able to keep the total expected cost, $2,193,910 ($420,000 plus $1,773,910) to within 8.1% ($163,910) of engineer�s estimate.
It is in the City�s best interest to accept J. Fletcher Creamer�s bid. There are several reasons why staff urges acceptance of this bid:
Acceptance of the bid would also make moot the issue of whether to delay or terminate implementation of UUD#1 due to significantly increased construction costs.
BWP�s share of the $1,773,910 is $1,288,538. Each utility�s cost is based upon:
Communication companies accept this cost allocation method, which is modeled on that of Anaheim, a city with long experience in managing underground utility districts.
BWP�s share of the cost is about three-quarters of the total:
TABLE 1. ALLOCATION OF COSTS AMONG UUD#1 PARTICIPANTS
Given that the engineer�s estimate for the total is $1,610,000, the engineer�s estimate for BWP�s share would be $1,169,504 (72.64% of $1,610,000); the expected cost of $1,288,538 is $119,034 (10.2%) higher. (Note that Abovenet�s amount includes not only the $30,000 in installed costs mentioned earlier, but also $17,028 in shared costs that would otherwise be borne by BWP and the other utilities.)
As of January 12, 2006, Charter Communications and Abovenet have assented in writing to the cost allocation; the former by letter, and the latter by e-mail. Verizon Wireless has given its verbal approval, while AT&T has not yet confirmed their approval. All the participants understand that they are to reimburse BWP their allocated share, based on this latest bid, by July 31, 2007.
The undergrounding work under Bid Schedule 1225 is still within budget for UUD#1. Because of the delay of obtaining a bid close to the engineer�s estimate, hardly any funds have been spent yet on UUD#1 besides some in-house engineering labor. The amounts budgeted for this fiscal year (2007-08) and the next (2008-09) total $2,451,000. Of this amount, $1,288,538 is needed to cover the cost of installing conduit and maintenance vaults, which, as mentioned earlier, is $119,034 more than the engineer�s estimate. Nevertheless, the remaining $1,162,109 is still sufficient to cover BWP�s cost of installing power and fiber optic cables. The cable had already been purchased at favorable prices; and the installation would be done in house.
The $420,000 for conduit and maintenance vault installation along Lake Street, which was to be part of UUD#1 Project expenditures, will now be included as FY 2008-09 Replacement Burbank Station Project expenditures.
The undergrounding work within UUD#1 is categorically exempt under the California Environmental Quality Act (CEQA). The exemption falls under the provisions of Paragraph 15302, Class 2(d) of �Guidelines For Implementation of the California Environmental Quality Act� as adopted by the Secretary for Resources of the State of California, June 1992 or the latest revision. According to the State�s Secretary for Resources, converting overhead facilities to underground, and restoring the streets to as good or better condition, does not have a significant effect on the environment and is declared to be categorically exempt.
BWP had filed a Notice of Exemption in the office of the Community Development Department�s Planning Division on May 31, 2006, for 21 days of posting.
FISCAL IMPACT STATEMENT
Awarding the contract to J. Fletcher Creamer and Sons would not have an adverse impact on BWP (Fund 496). Work on both UUD#1 and the Replacement Burbank Station remains within project budgets. Approving the allocation of undergrounding costs between BWP and the several communication utilities would have a positive fiscal impact. The allocation reflects some of the cost-sharing advantages of forming an underground utility district.
RECOMMENDATION
Staff recommends that Council adopt a Resolution approving plans and specifications, and awarding a contract to J. Fletcher Creamer and Sons to install a conduit system for the Olive Avenue Underground Utility District No. 1 (UUD#1) for $1,773,910 (Bid Schedule 1225) and approving the cost allocation detailed in Table 1 of this staff report, and specifying that the four communications utilities must fully reimburse BWP by July 31, 2007.
If the Council concurs, the appropriate action would be motions to adopt the following resolution:
A RESOLUTION OF THE COUNCIL OF THE CITY OF BURBANK APPROVING AND ADOPTING CONTRACT DOCUMENTS, PLANS AND SPECIFICATIONS, AND DETERMINING THE LOWEST RESPONSIBLE BIDDER, ACCEPTING THE BID, AND AUTHORIZING EXECUTION OF A CONTRACT TO INSTALL A CONDUIT SYSTEM FOR UNDERGROUND UTILITY DISTRICT NO. 1 � OLIVE AVENUE (BID SCHEDULE 1225) TO J. FLETCHER CREAMER AND SONS IN THE AMOUNT OF $1,773,910, AND APPROVING AN ALLOCATION OF THE COST OF SUCH WORK AMONG BURBANK WATER AND POWER AND OTHER COMMUNICATION UTILITIES.
GLS:DDB:jg L:\City Council\Staff Reports\2007\Olive Ave. Underground Utility District No. 1.doc
Attachments: Staff Report dated June 20, 2006 Resolution No. 27,255
c: Bonnie Teaford-Public Works Rick Morillo-City Attorney�s Office Kristy Shadle -Purchasing Division
|