Council Agenda - City of Burbank

Tuesday, October 3, 2006

Agenda Item - 4


 

 
                                              CITY OF BURBANK
                                 PUBLIC WORKS DEPARTMENT
                                                MEMORANDUM

 
 

 

DATE: October 3, 2006
TO: Mary J. Alvord, City Manager
FROM:

Bonnie Teaford, Public Works Director

By: Bob Van Hazelen, Assistant Public Works Director � Fleet & Building

SUBJECT:

RESOLUTION AUTHORIZING THE ACCEPTANCE OF GRANT FUNDS FROM THE CALIFORNIA OFFICE OF EMERGENCY SERVICES FOR SEISMIC RETROFIT OF FIVE MUNICIPAL BUILDINGS AND DESIGNATION OF AGENTS TO EXECUTE DOCUMENTS ON BEHALF OF THE CITY


 

PURPOSE:

 

To obtain Council approval of a resolution authorizing the City Manager to accept grant funds from the California Office of Emergency Services (OES) as a sub-grantee of the Federal Emergency Management Association (FEMA) Grant No. 20050011, OES No. 037-08954, Project No. PJ46 in the amount of $1,439,791, and to designate the City Manager or her designees, the Public Works Director and the Assistant Public Works Director- Fleet and Building, as authorized agents to execute documents relating to processing of this grant.

 

BACKGROUND:

 

In April 1999, the Council adopted Ordinance No. 3512[1], which required owners of buildings constructed before 1980 that have reinforced masonry or reinforced concrete walls to evaluate those structures.  If the evaluation indicated that a building did not meet minimum standards for structural seismic resistance, the owner would be required to strengthen it. These mandatory seismic improvements did not preclude an owner undertaking more extensive strengthening; in fact, the City also adopted voluntary guidelines that, if implemented, could further improve a building�s seismic performance. 

 

Forty-eight City-owned[2] buildings that were constructed before 1980 were found to have reinforced masonry or reinforced concrete walls, and thus were subject to the mandatory evaluation requirement.  When these 48 structures were evaluated in 2001, it was determined that 20 City-owned buildings require seismic retrofit in order to comply with the mandatory ordinance.  A preliminary multi-year schedule for implementing the work was developed after discussions with the various building users (Fire Department; Police Department, Parks, Recreation and Community Services; various Public Works divisions, etc.), and funds have been accumulating in the Seismic Retrofit Revenue Account to pay for the work.

 

In February 2005, staff applied for hazard mitigation grant funding from OES (as a sub-grantee of FEMA grant No. 20050011) for nine buildings that had been included in the first phase of work.  Three separate grant applications were submitted for mandatory and voluntary seismic retrofitting of the following facilities:

  • Fire Station 16

  • Three recreation centers (Verdugo, Olive, and McCambridge)

  • Five other buildings

  • Refuse Locker Room

  • Water Reclamation Plant Administration Building

  • Public Works Field Services Administration Building

  • Police Pistol Range

  • Starlight Amphitheater

In May 2006, staff received notice from OES that FEMA approved the $1,439,791 grant application for the five buildings, and denied the grant applications for Fire Station 16 and the three recreation centers (no explanation for the denial was provided).  As part of the grant approval process, the City is required to designate at least one agent to authorize documents for processing reports, reimbursement requests, and all other matters pertaining to the grant.

 

ANALYSIS:

 

The retrofitting of the five buildings for which the grant was received is estimated to cost $2,520,832, as indicated in Table 1.  The grant will reimburse up to 75 percent of these estimated costs.  In order to receive these funds, Council must formally accept the grant and designate at least one agent to act on behalf of the City for matters pertaining to the grant.  Staff recommends that Council designate the City Manager or her designees, the Public Works Director and the Assistant Public Works Director- Fleet and Building, to serve in this capacity.

 

Table 1

 

Estimated Construction Costs and Construction Schedule

 

Construction

Year

Building

Estimated

Construction

Costs

06-07

Refuse Locker Room

          $   248,422

06-07

Water Reclamation Administration Building

               785,798

06-07

Field Services Administration Building

               450,028

06-07

Police Pistol Range

               564,285

06-07

Starlight Amphitheater

               243,132

Total Construction Cost Estimate

         $ 2,291,665

Architecture & Engineering Design Costs

               229,167

Total Construction plus A&E Costs

         $ 2,520,832

 

FISCAL IMPACT:

 

The proposed resolution accepts the grant funding of $1,439,791. The Seismic Retrofit Project is funded from four separate funds. Upon receipt of the reimbursement money from the OES, the funds will be deposited into the account numbers listed below to reimburse the Funds accordingly.

 

370 Fund: 370.ND000.48010.1093 (Seismic Retrofit Revenue Account) $383,479

534 Fund: 534.ND000.48010.1093 (Seismic Retrofit Revenue Account) $212,066

494 Fund: 494.ND000.48010.1093 (Seismic Retrofit Revenue Account) $727,183

498 Fund: 498.ND000.48010.1093 (Seismic Retrofit Revenue Account) $117,063

 

RECOMMENDATION:

 

Staff recommends Council approve the resolution authorizing the City Manager to accept grant funds from the OES as a sub-grantee of the FEMA Grant No. 20050011, OES No. 037-08954, Project No. PJ46 in the amount of $1,439,791 and to designate the City Manager or her designees, the Public Works Director, and the Assistant Public Works Director as authorized agents to execute documents and all matters relating to this grant.


 


[1] Ordinance No. 3512 is entitled �An Ordinance of the Council of the City of Burbank Amending Chapter 7 of the Burbank Municipal Code Requiring Seismic Retrofit of Existing Reinforced Concrete Wall and/or Reinforced Masonry Wall Buildings with Flexible Diaphragms,� also called the �mandatory seismic retrofit ordinance�

[2] For the purpose of this report, �City-owned� means non-Burbank Water and Power facilities

 

 

go to the top