Council Agenda - City of Burbank

Tuesday, August 29, 2006

Agenda Item - 4


 

 
 
 

 

DATE: August 29, 2006
TO: Mary J. Alvord, City Manager
FROM:

Bonnie Teaford, Public Works Director

by:  Bob Van Hazelen, Assistant Public Works Director - Fleet & Building

SUBJECT:

                     RESOLUTION APPROVING CHANGE ORDER NUMBER 1 FOR BID SCHEDULE NO. 1197, PUBLIC WORKS UNDERGROUND TANK RETROFIT PROJECT 

 


PURPOSE: 

Staff is requesting Council approval for Change Order Number 1 for Bid Schedule No. 1197, Public Works Underground Tank Retrofit Project  

BACKGROUND 

On February 7, 2006, Council approved contract documents and awarded the construction contract to West Star Environmental, Inc. for Bid Schedule No. 1197, Public Works Underground Tank Retrofit Project.  Staff�s report to Council included a recommendation to award the contract not only for the base bid amount, but also for additional work item options totaling $169,532.00.  The additional work items were for anticipated work that is typically needed when underground tanks are uncovered. Council approved awarding the base bid and the work item options; however, the work item options were omitted from the resulting resolution number 27,165, which stated only the base bid amount of $739,446.00 (not the base bid plus options total of $908,978.00)

ANALYSIS: 

As the project has progressed, it has been confirmed that $115,883.00 of the previously identified potential additional work items need to be completed (Table 1).  There have also been additional items discovered that require correction, which will cost $28,872.62 (Table 2). Change Order No. 1 in the amount of $144,755.62 ($115,883.0 plus $28,872.62) will increase the total contract price to $884,201.62.  This is a 19.5 percent increase in the original contract amount, but still below the $908,978.00 of the originally contemplated base bid plus options total.  In addition, the change order will extend the date of completion to October 13, 2006, as an additional 41 work days will be required to complete the necessary items.

Table 1

Previously Identified Work Items

DESCRIPTION

TOTAL

Replace generator piping at Station #14

$27,136.00

Replace generator piping at Station #15

$11,859.00

Replace product piping at NORTH product tank PW YARD � Site A

$36,099.00

Replace product piping at SOUTH product tank PW YARD � Site C

$6,713.00

Replace sump and piping at the parks pesticide tank.

$27,178.00

Install tank collars on both tanks at Station #12

$6,898.00

TOTAL

$115,883.00

 Table 2

Additional Work Items

DESCRIPTION

TOTAL

Install new wider manways to eliminate water intrusion into pumps.

$11,850.00

Replace sump pump manway at Station #15

$1,840.00

Replace rusted sump manway at Station #14

$1,840.00

Replace corroded electrical conduit at Station #15

$395.00

Replace manway gaskets on tank at Station #14

$750.00

Replace manway gaskets on tank at Station #15

$750.00

Repair leak at fiberglass bung at Station #15

$650.00

Repair leak at fiberglass bung at Station #14

$650.00

Upgrade sensors on pesticide tank for extended life

$1,849.87

Extra concrete work to fill in area between tank pad and dispenser at Station #14

$478.98

Replace vent and vapor piping at the Golf yard

$750.00

Replace vent and vapor piping at Station #13

$7,068.77

TOTAL

$28,872.62

FISCAL IMPACT

The original contract amount is $739,446.00. This change order request increases the contract amount to $884,201.62. Sufficient funds are available in the appropriated budget for this change order in account number 534.PW33A.15032.0000.16572 (Underground Tank Retrofit Project).

RECOMMENDATION

Staff recommends that the Council adopt the proposed resolution approving Change Order No. 1 for Bid Schedule No. 1197, Underground Tank Retrofit Project.  

 

Attachment: Change and Extra Work Order No. 1

 

 

 

go to the top