Council Agenda - City of BurbankTuesday, July 11, 2006Agenda Item - 1 |
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
WATER UPDATE
Water Quality
Financial and Operations Update
( ) = Unfavorable * Includes Power Plant Sales, Commercial and Industrial Reclaimed Sales (A) Deferring WCAC revenues reduced potable water revenues by $453k FYTD. (B) The actual YTD recycled water sales are lower due to MPP operations. (C) The BOU has experienced reduced operating capacity due to carbon screen failures, water production problems associated with a persistently low water table, and well maintenance. The lower BOU operating capacity increased the need to purchase water from the Metropolitan Water District (MWD) which resulted in higher than planned costs. The BOU has operated at an average operating capacity FYTD of 58%, compared to a budget of 75%. (D) Reconciliation of Deposit Accounts.
Fiscal Year 2005-06 Water Fund Financial Reserve balances as of May 31, 2006 are summarized in the following table:
BOU Water Production
Environmental Protection Agency (EPA)
Capital Projects
Legislative Update
ELECTRIC UPDATE
Electric Reliability
There were three 4 kV feeder outages in May. These outages interrupted service to 844 customers for a total of 320 minutes.
Despite the power outage in May, BWP�s overall reliability continues to be strong. As of May 31, 2006, the system-wide average is 0.3443 outages per year, compared to an industry average of 1.2 outages per year. As of May 31, 2006, the average service availability is 99.995%, exceeding the City goal of 99.99%. The average outage length is 69.74 minutes, compared with the industry average of 80 minutes.
The following table shows the system-wide reliability statistics for Fiscal Year 2005-06 through May 31, 2006, as compared to the same time period for Fiscal Year 2004-05:
Financial and Operations Update
( ) = Unfavorable (A) New transmission revenue related to MPP scheduling services. YTD impact is $1,000k. (B) Power Supply variance is primarily due to cost of natural gas, spot energy and replacement power associated with MPP COD delay and planned outages. (C) Other Income included a BPA settlement of $591k, and supplemental crude oil refund of $130k. Actual interest income is higher than budget due to higher interest rates. Budget assumes interest rate of 2.5% APR. Actual interest rates are between 4%-5%. Estimated FYTD impact of higher interest income is $900k.
Fiscal Year 2005-06 Power Fund Financial Reserve balances as of May 31, 2006 are summarized in the following table:
Local Generation Operations Update
Unit Status
May 2006 Unit Data
Magnolia Operations Update
Workforce Safety Statistics:
Actions Taken by Operating Agent:
Renewable Energy Procurement Update
Work continues in conjunction with the SCPPA project team on various renewable energy projects. All project specific information needs to remain confidential until a project agreement is brought to Council for approval. This is to protect the business interests of the proponents and to ensure that the terms and conditions associated with their proposals don�t fall into the hands of competitors.
During the month of May there were again numerous meetings and conference calls with project proponents. We remain optimistic that we will have at least one purchased power agreement ready for approval shortly, with deliveries expected this summer. The plan is to use that contract as the template for another purchased power agreement from the same developer for an additional project. Deliveries from this second project are currently expected to begin in mid-2008.
The solar energy developer is still working on providing additional costing information for the project based on flat pricing as opposed to the escalating proposal previously presented. A follow-up meeting that was scheduled with the developer for mid-May was cancelled in order to give him more time to work on the analysis. It is expected that a meeting will be held in June.
SCADA/EMS
BWP engineering staff continues to work with Siemens New Energy to implement the New Energy Scheduling software that is being used for Magnolia. The OATI Web Trader is operational.
The Test Section was able to get the updated firmware and they started installing the 2300 CPU cards into the Remote Terminal Units (RTUs).
The Factory Acceptance Testing was done in Houston during May. The test was completed satisfactorily.
The SCADA Master Station is being configured by Telvent in Houston and should be ready for shipment to BWP in the first part of June.
Telecom
Engineering developed a fiber optic service proposal for Warner Brothers to connect Warner Building 157 at 4000 Warner Boulevard to 2101 W. Olive Avenue.
Engineering developed a fiber optic service proposal for FotoKem to connect their main facility at 2801 W. Alameda Ave. to 2950 Hollywood Way.
Engineering personnel released, and BWP field personnel completed, a fiber optic job to connect a temporary link from the following substation multiplexer fiber connections:
Engineering personnel released, and BWP field personnel completed, a fiber optic job for Warner Brothers to connect Warner Building 157 at 4000 Warner Boulevard to Pinnacle #2 at 3300 W. Olive Avenue.
Engineering personnel released, and BWP field personnel completed, a fiber optic job for OnFiber to connect NBC Studios at 3000 W. Alameda Avenue to BWP�s Hollywood Way Substation.
Engineering personnel released, and BWP field personnel completed, a fiber optic job to connect and re-route a link for the relays associated with the Lincoln-Capon 69 kV line.
Engineering personnel released, and BWP field personnel completed, a fiber optic job to relocate a major fiber hub that was located in the basement of the MPP Service and Control Building to a new room on the first floor. This project required coordination with all of BWP�s fiber customers, cutting and re-routing ten (10) fiber cables, and the completion of 1400 fiber splices.
Engineering personnel completed a fiber optic job to connect a temporary link from BWP�s Olive GIS Station to the Lincoln Substation relay house.
Engineering personnel completed a fiber optic job to connect a temporary link from the Olive Station to the Western Station in Glendale.
BWP Facility Improvements
BWP Administration Building - Phase III Interior Remodel
Plans and construction drawings received approval from CDD, Fire, Police, and BWP�s Electrical, Water and Telecom sections. Project specifications are being reviewed by Purchasing to begin the bid process for a contractor.
Employee Entrance Project
This project involves the installation of a new proximity card operated, turnstile equipped entrance/exit for employees off of the Magnolia parking lot. The contractor, H&H Construction, is 90% complete. The remaining tasks include the installation of the turnstile and ADA gate, painting of the block wall, and landscaping. BWP crews will install the lighting, security camera, intercom, and the proximity card reader to activate the turnstile.
Magnolia Covered Parking
This project involves modifying the existing area east of the Magnolia employee covered parking lot to create additional covered employee parking spaces. A new ingress/egress opening will be made in the existing wall, the structure will be pressure washed and painted, new lighting will be installed, a chain link fence will be added, and the area will be paved and striped. BWP staff completed the relocation of all the equipment and material that was stored in the designated area. The remediation contractor removed all of the lead paint. BWP painters began pressure washing the structure in preparation for painting. New lighting has been ordered and will be installed by BWP electricians. The remaining tasks involve paving the area, installing chain link fencing, and saw cutting the new opening in the block wall.
Magnolia Security Wall
This project involves constructing a new 320 foot long security wall along the southerly side of the Magnolia covered parking lot, east of the Magnolia gate. The wall will be identical in height to the wall on the west side of the gate and will correct security concerns identified during the construction of MPP. Preliminary construction drawings and specifications were reviewed by BWP staff and are ready to be finalized. A determination remains as to whether this work will be done in-house or sent out for competitive bids.
BWP Service Center and Warehouse Project
BWP staff has been working with the SGS Group, a consultant hired to perform the programming and space needs assessment study for a new Service Center and Warehouse to be constructed on BWP�s campus. A Professional Services Agreement was drafted and approved for architectural services to be provided by the Kennard Design Group (KDG). SGS presented the final version of the space allocation and needs assessment documents. A kick-off meeting was held with KDG and their project team, and a site walk was conducted.
Electrical Distribution
69,000-Volt Transmission System
At the Golden State Distributing Station, field crews upgraded the 69 kV bus differential relays for the 69 kV sectionalizing breaker. Final testing was completed and in mid-May the breaker was closed. BWP crews have extensively cleaned, maintained and tested the 12.47 kV portion which will forestall future outages due to equipment failure.
At the Lincoln Switching Station, field crews replaced four out of the five 69 kV breakers, and expect to replace the fifth breaker in June.
Contruct a new Olive-Valley #2 Line - The consultant, ORSA, has completed the design for pads and underground power conduits for the extension of the ring bus at the Valley Switching Station. Bock Company has completed the work inside the substation and in the direction of Ralph Foy Park. BWP Engineering completed work on the design to extend power conduits stubbed at Victory Blvd. through the park toward Ontario St. and near Victory Blvd. and Fairview St., to complete the underground getaway of this line. Bock will continue to work on street conduit work related to this line until its completion which is estimated to be by July 14, 2006. The preliminary design of ground grid and equipment pads was completed and issued for comments.
34,500-Volt Subtransmission System
Between the Olive Switching Station and the Burbank Substation, field crews upgraded the underground cable to increase the capacity of the Burbank-Olive #2 line and upgraded the relay protection. The remaining underground cable work including termination, cable support, cable enclosure and protection work started on June 2, 2006. It is estimated to be completed by June 9, 2006 before final testing is scheduled on the line. The line is estimated to be energized by June 16, 2006 along with the A-5 transformer bank at the Olive Switching Station.
34,500-Volt Distribution System
At the Winona Distributing Station, field crews upgraded relay and control switches for the Winona Industrial Circuit in preparation for reconfiguring the line.
Field crews completed the Warner Ranch Industrial Circuit.
12,470-Volt Distribution System
Under engineering direction, field crews converted the 4 kV Feeder A-7 to 12 kV service from the new Hollywood Way Station (HW-7). As a part of this effort, four customer stations were rebuilt to 12 kV.
Under engineering direction, field crews are rebuilding the A-96, A-97, and A-8 overhead lines so that they can be energized from the Hollywood Way Station this fall.
Progress continues on rebuilding deteriorated pole lines and single pole replacements.
In May, crews continued working on the pole line rebuilds in the A-96 and A-97 Feeder areas. Crews are framing the poles and replacing conductors to prepare for the 12 kV conversion. Crews are also working on the pole line rebuild on Ontario St. south of Wyoming Ave.
4,160-Volt Distribution System
At the McCambridge Station, field crews replaced the main batteries. BWP crews replaced approximately 500 circuit feet of old and ready to fail underground cable at 4.16 kV circuit Flower-4. This cable was approximately 50 years old. The new cable went into service in mid-May.
Secondary Voltage System and Electric Metering
Customer Transformer Stations
New business, and a strong residential real estate market, has created a demand for new customer stations.
Engineering has completed the design for the Bob Hope Airport Remote Lot A. The new padmount transformer service, and the existing FAA Tower service, will be fed underground from Winona Avenue via a new padmount switch. The design includes a new underground source of feed for streetlighting on Hollywood Way. After construction completion, the existing power poles will be removed.
Undergrounding
BWP has worked with the City Attorney�s Office, the Public Works Department, and the Community Development Department in forming Underground Utility District 1 (UUD1) to underground all overhead lines (power and communications) along Olive Ave. from the I-5 Bridge to Victory Blvd., and along Lake St. from Olive Ave. to Magnolia Blvd. BWP has been successfully working with SBC, Charter Communications, and other affected communication companies as well as the affected customers. On May 30, 2006, the City Council passed a Resolution of Intention. A public hearing is set for June 20, 2006, as well as a resolution authorizing the City to establish the UUD1.
BWP removed all energized overhead lines immediately behind the former Buena Vista Library building.
BWP engineering issued a job to replace approximately 1,420 circuit feet of 35 kV Paper Lead Insulated Cable (PILC) at the Burbank-Flower line. This was scheduled to be completed by June 15, 2006 and is on schedule.
BWP Engineering is working on two projects related to Caltrans. One project involves the Alameda, Hollywood Way and Pass Ave. bridge widening on the SR-134, and a new on-ramp at Hollywood Way. The second project involves the I-5 freeway, Empire Exchange, and San Fernando Realignment. Staff is working with consultants and Caltrans on design work that requires relocation of existing underground and overhead facilities.
Streetlighting System
In response to customer requests, field crews installed one light in April (15 since July).
Engineering is preparing drawings for the undergrounding of the streetlight system on Olive Ave. and South San Fernando:
Engineering continues working with the Redevelopment Agency on the South San Fernando Blvd. street improvement project, and with the Public Works Traffic Signal Division on other street/traffic improvement projects, especially the Empire Avenue Streetscape Project. The San Fernando Intelligent Transportation System Project is under construction. In May, construction was started on the Olive/Alameda Intersection Widening Project.
Radios
All systems are working.
The police MDT radio crashed and was repaired. The first of the new radios (XTS 2500) arrived but the balance are backordered. The plan to replace the remaining City radios beginning in June will be pushed back at least one month.
Phones and Miscellaneous
All systems are working.
Staff is looking at a new phone switch for MPP.
Customer Service
The power of the City of Burbank�s bill inserts has once again been proven. In May, we ran a bill insert highlighting BWP�s Home Energy Analyzer service. This free online service allows Burbank residents to quickly discover ways in which they can reduce energy and water usage at their homes. As a result of the insert, 139 visits to the Home Energy Analyzer site were logged during May, up from 46 the previous month.
Legislative Update:
Refer to the attached legislative reports.
RED:BL:FCF:WOM:GLS:JLF H: JUNE W&E OPERATIONS REPORT