|
Council Agenda - City of BurbankTuesday, August 31, 2004Agenda Item - 11 |
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
WATER UPDATE
Water Quality
( ) = Unfavorable * Excluding Power Plant sales. ** Source: Budget 2004-05.
Fiscal Year 2004-05 preliminary Water Fund Financial Reserve balances as of July 31, 2004 are summarized in the following table:
Environmental Protection Agency (EPA)
Capital Projects
Legislative Update
ELECTRIC UPDATE
Electric Reliability
The following table shows the systemwide reliability statistics for Fiscal Year 2004-05 as compared to Fiscal Year 2003-04:
Financial and Operations Update
( ) = Unfavorable * Actual MWh sales differ from budget MWh due to timing of customer billing. ** Source: Budget 2004-05.
Local Generation Operations Update Unit Status
July 2004 Unit Data
Power Supply
There were no significant developments regarding this matter in June. In May 2004, FERC decided that it will no longer work directly with BWP on the $6 million refunding issues. BWP must seek refunds through Sempra Energy Trading. BWP has contacted Sempra Energy Trading and is currently working on a mutually acceptable resolution to recover costs through Sempra.
Engineering and fabrication work associated with this project continues on budget with a scheduled date of late 2004.
SCPPA members interested in procuring natural gas reserves in the ground have received their Council�s approvals to proceed. BWP has initially committed to acquiring 1,000 Dekatherms per day (Dth/day) through the program, which represents approximately 5% of future expected annual requirements. The viability to proceed is expected this fall.
Magnolia Power Project (MPP)
The items in this report are provided as a general overview of the status of the Project. These items are discussed in considerable detail among the Project Participants at the Project Coordination Meeting each Friday and at Coordinating Committee meetings.
Safety
Through July, Kvaerner has worked 340,231 man-hours with no lost time cases and three recordable cases.
Budget
Refer to the attachment for detailed information on actual expenditures for the period ending July 31, 2004.
Schedule
The project remains on schedule for a commercial operation date of May 25, 2005. Refer to the attachment for detailed information on Project milestones.
Finance
The Magnolia Power Project Finance Committee continues to review refunding proposals and has taken no action regarding the refunding of Project A bonds.
California Energy Commission (CEC) Compliance
No violations of conditions have occurred.
Engineering, Procurement and Construction Activities since last Project Director�s Report of July 12
Transmission
Coordinating Committee Action
There was no meeting held in July.
Project Manager�s Actions Since Last Project Director�s Report of July 12
With consultation and agreement from Project Participants, the following actions have been taken:
Key Milestones and Anticipated Significant Activities For Next 30 Days
Power Supply Capital Projects
Work began to make the advanced software applications operational on the Telvent SCADA.
The OATI Scheduling and Transaction Management System (STMS) software acceptance testing continued in July. The bandwidth of the internet connection between OATI and BWP was doubled in an attempt to improve the responsiveness of the OATI software. Testing did not show a marked improvement. OATI is still working to provide net schedules on transmission lines. BWP has informed OATI that resolving the speed issue has reached a critical point that needs quick resolution.
Engineering provided a proposal to New Wave Entertainment at 2660 W. Olive Ave. and Warner at 3400 Riverside Dr.
Field personnel completed a fiber optic job to connect Warner Building 157 at 4000 Warner Blvd. to Warner Ranch, 3701 Oak St.
Field personnel completed a fiber optic job to disconnect a temporary station multiplexer and 60 kV relay connections.
Field personnel completed a fiber optic job to reconnect Disney Feature Animation South to Disney, 640 Paula Ave.
The first iteration of programming for the individual offices and workstation furniture was completed. Isometrics are being developed for review before being finalized. Chairs for all personnel were selected and will be ordered shortly.
Construction work for extending the ducts and manholes along Oak St. from California St. to Buena Vista and along Buena Vista to Edison Rd. is completed. Underground cable has been delivered and the cable installation is approximately 90% complete.
In July, thirty nine power poles were replaced, including the pole line in the Media District. BWP Electrical Engineering is designing a pole line rebuild in the area between Clybourn and Pass Aves. north of Verdugo Ave. In addition to pole replacements, a large area in the Media District is being rebuilt to 12 kV standards in preparation for the future transfer of some Alameda feeder loads to the new Hollywood Way Station.
In July, two pad mounted customer stations were engineered and issued to the field; three pad mounted transformers for Burbank Village Walk and relocation/upgrade of the pad-mounted transformer feeding the Burbank City Employees Federal Credit Union. Service to the second phase of Burbank High School has been energized.
Construction is in progress for the second phase of the streetlight system undergrounding on Magnolia Blvd. between Pass Ave. and Buena Vista St. The private contractor, Steiny and Company, Inc. is installing streetlight conduits. The work is scheduled to be completed in August.
Replacement of the remaining oil switches with pole mounted airbreak switches has been issued to the field with the exception of one, Pacific-16 distributing switch, which will be removed during the unloading of this feeder scheduled for November 2004.
Construction of the new Hollywood Way Substation, and transfer of load from the old Hollywood Way Station, is 100% complete. Construction of the new off-ramp was completed on June 30, 2003. The Hollywood Way Substation was completed and energized on March 1, and the remaining testing was completed by March 8. The dedication ceremony took place on March 30 and the load transfers were completed by April 30. By May 12 2004, five lines were reconfigured to connect from the Capon Switching Station, which completes the work scheduled for this fiscal year. The old Hollywood Way Station is completely de-energized and the equipment is still on the pads ready to be removed when needed. The Community Development Department (CDD) Transportation and BWP are working on an interim landscaping plan for the front of the Hollywood Way and Alameda Substations due to the delay in construction of the SR-134 on-ramp project by Caltrans. The interim landscape plan would be implemented very soon.
The Southern California Public Power Authority (SCPPA) awarded a contract to ABB Inc. to design/build the Gas Insulated Switchgear (GIS) expansion at the Olive Switching Station. This will connect the Magnolia Power Plant to the Olive Switching Station. ABB had two design review meetings with staff and submitted the design for Chief Building Officer (CBO) approval in the first week of February 2004. Construction started at the end of March as scheduled. The GIS equipment is manufactured, tested, and ready to be shipped. The GIS equipment, control building, and all protection and controls arrived on site in June 2004. All GIS and control/protection equipment was set on the pad and assembly work is in progress.
Bock Co. has completed the installation of a new underground duct system in the BWP Yard to underground two 69,000 volt overhead lines as a part of BWP�s overall plan to improve and modernize the BWP generating site. Both riser poles north of the Magnolia Bridge are completed along with cables to the first manholes at the northeast corner of the BWP Yard. Cable and all other related materials are ordered. This work is expected to be completed before MPP goes on-line. The 69 kV cable for the Olive-Lincoln lines will be shipped on August 23, 2004.
The 69,000 volt underground cable and devices were ordered for making the connections from MPP to the Olive Switching Station. The GSU and other related power transformers were manufactured, tested, and shipped from Turkey in early June 2004. These transformers arrived on the site and set on the pads. The 69 kV cable delivery will be shipped on August 28, 2004.
BWP staff is working on the Olive Switching Station retrofit by upgrading circuit breakers, busses and other equipment. This upgrade is needed for the Magnolia Power Project. Approximately 40% of the work is completed.
BWP Electrical Engineering has completed the design for the new underground ducts installation along Verdugo Ave. from Kenwood to California St. Bock Co. started work on this project on July 12, 2004.
BWP Electrical Engineering is working with the Community Development Department (CDD) and Public Works Department to install ducts for the underground distribution system in the South San Fernando Redevelopment area as a part of streetscape work if funding is approved.
A total of 1,823 remote meters were installed during Fiscal Year 2003-04; 851 were requested by the Customer Service Division, and 972 were meter change-outs performed by the Line Crews or Test Shop.
Legislative Update:
Refer to the attached legislative reports.
RED:RAC:FCF:JWL:GLS:JLF H:JULY W&E OPERATIONS REPORT
Attachments
|