|
Council Agenda - City of BurbankTuesday, July 27, 2004Agenda Item - 10 |
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
WATER UPDATE
Water Quality
Financial and Operations Update
( ) = Unfavorable * Excluding Power Plant sales.
Note: There was a payment of approximately $900k for principal and interest on Fund 497 Bonds due on June 1, 2004.
Environmental Protection Agency (EPA)
Capital Projects
Legislative Update
ELECTRIC UPDATE
Electric Reliability
The following table shows the systemwide reliability statistics for Fiscal Year 2003-04 as compared to Fiscal Year 2002-03:
Financial and Operations Update
( ) = Unfavorable
* Note: There is a payment of approximately $8.8 million for principal and interest on Fund 496 Bonds due on June 1, 2004.
Local Generation Operations Update
Unit Status
June 2004 Unit Data
Power Supply
� FERC Data Requests and Refund Calculation
There were no significant developments regarding this matter in June. In May 2004, FERC decided that it will no longer work directly with BWP on the $6 million refunding issues. BWP must seek refunds through Sempra Energy Trading. BWP has contacted Sempra Energy Trading and has worked on a mechanism to recover costs.
� Restructuring of the Gas Industry in Southern California
As reported last month, restructuring of the gas industry in Southern California was put on hold by the California Public Utility Commission (CPUC) on May 27. There has been no major development since.
Future changes to the way intra-state pipeline capacity is allocated on the SoCalGas system may arise out of the Gas Industry Restructuring Order (�GIR�) investigation on SoCalGas� intrastate pipeline later this summer.
� Sylmar Converter Station Replacement Project
Engineering and fabrication work associated with this project continues on budget with a scheduled date of late 2004.
� SCPPA Natural Gas Reserve Procurement
On June 29, Council authorized BWP to participate with other SCPPA members to look into the feasibility of procuring natural gas reserves in the ground. BWP has initially committed to acquiring 1,000 Dekatherms per day (Dth/day) through the program, which represents approximately 5% of future expected annual requirements. The viability to proceed is expected this fall.
Magnolia Power Project (MPP)
The items in this report are provided as a general overview of the status of the Project. These items are discussed in considerable detail among the Project Participants at the Project Coordination Meeting each Friday and at Coordinating Committee meetings.
Safety
Through June, Kvaerner has worked 288,198 man-hours with no lost time cases and three recordable cases.
Budget
Refer to the attachment for detailed information on actual expenditures for the period ending June 30, 2004.
Schedule
The project remains on schedule for a commercial operation date of May 25, 2005. Refer to the attachment for detailed information on Project milestones.
Finance
The Magnolia Power Project Finance Committee has reviewed refunding proposals and has taken no action regarding the refunding of Project A bonds.
California Energy Commission (CEC) Compliance
Excavation monitoring is substantially complete. Monthly reports are being made as required by the CEC. No violations of conditions have occurred.
Engineering, Procurement and Construction Activities since last Project Director�s Report of June 14, 2004.
Transmission
Coordinating Committee Action at its Meeting on May 20
There was no meeting held in June due to a conflict with the American Public Power Association Annual Meeting.
Project Manager�s Actions Since Last Project Director�s Report of May 17
With consultation and agreement from Project Participants, the following actions have been taken:
Key Milestones and Anticipated Significant Activities For Next 30 Days
Power Supply Capital Projects
� SCADA/EMS
The old Scipar SCADA hardware was removed from the SCADA Center.
A new SCADA Center Local Area Network (LAN) server was delivered and installed.
The OATI Scheduling and Transaction Management System (STMS) software acceptance testing continued in June. Work is continuing on improving the responsiveness of the OATI software and its ability to provide net schedules on transmission lines. BWP is currently working with the OATI and IT departments to resolve the speed issues.
� Telecom
Engineering provided a proposal to Universal Studios for fiber optic service connecting Universal Studios through Barham Blvd. to NBC Studios at 3000 W. Alameda Ave.
Engineering provided a proposal to Match Frame Video for fiber optic service connecting two of their facilities: 610 N Hollywood Way to 540 N Hollywood Way.
Engineering provided a proposal to Media Net for fiber optic service connecting the Disney Channel at 3800 W. Alameda Ave. to LADWP Receiving Station �E�.
Engineering provided a proposal to Turner Broadcasting for fiber optic service connecting Cartoon Network at 300 N. Third St. to Glenoaks Plaza at 303 N. Glenoaks Blvd.
Engineering provided a proposal to MeSoft for fiber optic service connecting FotoKem at 2815 W. Olive Ave. to LADWP Receiving Station �E�.
Engineering provided a proposal to Ascent Media for fiber optic service connecting Ascent Media at 2901 W. Alameda Ave. to Disney at 500 S. Buena Vista St.
Engineering released a job order to the Operations Section to restore the fiber optic ring connecting OnFiber to Qwest through the new Hollywood Way Substation.
Engineering released a job order to the Operations Section to provide fiber optic service re-connecting Disney�s D20 link � Disney Feature Animation to Disney at 640 Paula in Glendale.
Engineering released a job order to the Operations Section to reconnect the multiplexer SONET ring and 69 kV relay connections going through the Hollywood Way Substation. This work was completed.
Engineering released a job order to the Operations Section to provide fiber optic service connecting Warner Building 157 at 4000 Warner Blvd to Warner Ranch at Oak Street and Hollywood Way.
Field personnel completed a fiber optic job to connect SohoNet/Warner Building 157 at 4000 Warner Blvd. to West Olive Plaza at 3601 W. Olive Ave.
� BWP Administration Building Remodel
Signatures were secured for the final space allocation design (offices and workstations) for both the BWP Administration Building and the third floor of the MPP Service and Control Building. Schedules are now being developed for the next phase of the project which is the programming of the individual office and workstation furniture.
� Electrical Distribution
Construction work for extending the ducts and manholes along Oak Street from California St. to Buena Vista and along Buena Vista to Edison Rd. is completed. Underground cable has been delivered and the field crew is currently installing the cables.
Since July 1, 2003, a total of 168 pole replacements/installations have been issued to the field. A total of 124 poles have been replaced in this fiscal year. Replacement of a 30-pole line is under construction in the Media District area. In addition to pole replacements, a large area in the Media District is being rebuilt to 12 kV standards in preparation for the future transfer of some Alameda feeder loads to the new Hollywood Way Station.
Since July 1, 2003, 20 pad mounted customer stations have been engineered, two of which was engineered in June. Since July, there have been 14 pad mounted customer stations issued to the field and 17 pad mounted customer stations have been energized.
Since July 1, 2003, four series circuit conversions to low voltage have been completed and twenty-nine new streetlights have been installed. Three streetlight improvement and undergrounding projects have been issued and two have been completed. Construction has started for the second phase of the Magnolia Boulevard Project between Pass Ave. and Buena Vista St. The private contractor, Steiny and Company, Inc. is installing streetlight conduits.
Replacement of the remaining oil switches with pole mounted airbreak switches has been issued to the field with the exception of one, Pacific-16 distributing switch, which will be removed during the unloading of this feeder scheduled for November 2004.
Construction of the new Hollywood Way Substation, and transfer of load from the old Hollywood Way Station, is 100% complete. Construction of the new off-ramp was completed on June 30, 2003. The new Hollywood Way Station was completed and energized on March 1, and the remaining testing was completed by March 8. The dedication ceremony took place on March 30 and the load transfers were completed by April 30. By May 12 2004, five lines were reconfigured to connect from the Capon Switching Station, which completes the work scheduled for this fiscal year. The old Hollywood Way Substation is completely de-energized and the equipment is still on the pads ready to be removed when needed. The Community Development Department (CDD) Transportation and BWP are working on an interim landscaping plan in front of the old/new Hollywood Way and Alameda Substations due to the delay in construction of the SR-134 on ramp project by Caltrans.
The Southern California Public Power Authority (SCPPA) awarded a contract to ABB Inc. to design/build the Gas Insulated Switchgear (GIS) expansion at the Olive Switching Station. This will connect the Magnolia Power Plant to the Olive Switching Station. ABB had two design review meetings with staff and submitted the design for Chief Building Officer (CBO) approval in the first week of February 2004. The construction started at the end of March as scheduled. The GIS equipment is manufactured, tested, and ready to be shipped. The GIS equipment, control building, and all protection and controls arrived on site in June 2004.
Bock Co. has completed the installation of a new underground duct system in the BWP Yard to underground two 69,000 volt overhead lines as a part of BWP�s overall plan to improve and modernize the BWP generating site. Both riser poles north of the Magnolia Bridge are completed along with cables to the first manholes at the northeast corner of the BWP Yard. Cable and all other related materials are ordered. This work is expected to be completed before MPP goes on-line.
The 69,000 volt underground cable and devices were ordered for making the connections from MPP to the Olive Switching Station. The generator step-up (GSU) and other related power transformers were manufactured, tested, and shipped from Turkey in early June 2004. These generator and transformers are expected to arrive on-site on July 23-26.
BWP staff is working on the Olive Switching Station retrofit by upgrading circuit breakers, busses and other equipment. This upgrade is needed for the Magnolia Power Project and approximately forty percent of the work is completed.
BWP Engineering has completed the design for the new underground ducts installation along Verdugo Ave. from Kenwood to California St. Bock Co. is expected to work on this project starting in July 12, 2004.
BWP Electrical Engineering is working with the Community Development Department (CDD) and Public Works departments to install ducts for the underground distribution system in the South San Fernando Redevelopment area.
A total of 1,703 remote meters have been installed; 827 were requested by the Customer Service Division, and 876 were meter change outs performed by the Line Crews or Test Shop.
Legislative Update:
Refer to the attached legislative reports.
RED:RAC:FCF:JWL:GLS:JLF H:JULYW&E OPERATIONS REPORT
Attachments
|