|
Council Agenda - City of BurbankTuesday, May 4, 2004Agenda Item - 11 |
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
WATER UPDATE
Water Quality
Financial and Operations Update
( ) = Unfavorable
Environmental Protection Agency (EPA)
Capital Projects
Legislative Update
ELECTRIC UPDATE
Electric Reliability
The following table shows the systemwide reliability statistics through March 2004 for Fiscal Year 2003-04 as compared to Fiscal Year 2002-03:
Financial and Operations Update
( ) = Unfavorable (1) YTD Retail Revenue accrual is $ 1.3 million.
Local Generation Operations Update Unit Status
March 2004 Unit Data
Power Supply
The California Public Utility Commission�s (CPUC) Commissioners have approved a revised alternate of Judge DeUlloa�s Draft Decision by postponing implementation of the restructuring of SoCalGas Company�s intrastate pipeline system until a decision is made on SoCalGas Gas Capacity Rulemaking (R.04-01-025), which is expected this summer. There may be concerns regarding the decision because certain elements of the Comprehensive Settlement conflict with many proposals in the Gas Capacity Rulemaking. Due to the incompatibility of the two proposals, it is not clear how the plan will be implemented.
The engineering and fabrication work associated with this project continues on budget with a scheduled date of late 2004.
Magnolia Power Project (MPP)
The items in this report are provided as a general overview of the status of the Project. These items are discussed in considerable detail among the Project Participants at the Project Coordination Meeting each Friday, and at Coordinating Committee meetings.
Safety
Through March, Kvaerner has worked 155,586 man-hours with no lost time cases and two recordable cases.
Budget
Refer to the attachment for detailed information on actual expenditures for the period ending March 31, 2004.
Schedule
The project remains on schedule for a commercial operation date of May 25, 2005. Refer to the attachment for detailed information on Project milestones.
Finance
No Project A refinancing is planned at this time. The Magnolia Power Project Finance Committee has received eight refunding proposals since March 2004. The Magnolia Power Project Finance Committee has scheduled a meeting on May 4, 2004 to discuss these proposals.
CEC Compliance
Excavation monitoring continues pursuant to Conditions of Certification. Monthly reports are being made as required by the California Energy Commission (CEC). No violations of conditions have occurred. CEC staff visited the site on April 12.
Engineering, Procurement and Construction Activities since last Project Director�s Report of March 15, 2004.
Transmission
Facilities Agreement. Navigant has persuaded L.A. to agree to the correct percentages for the Project�s contribution to short circuit duty. The Agreement will require a provision that allows Magnolia to operate whether or not work on the L.A. system is performed.
Transmission Study Project. Magnolia participants are being polled to determine their level of interest in the Transmission Study. Personal Services Agreements will outline scopes of service on legal and regulatory issues associated with an interconnection with Southern California Edison.
Scheduled Services. Glendale will need two reactors at Western to fulfill its obligations for scheduled services. Delivery time for the reactors is about four months for standard orders. Don Allen is reviewing the primary agreements to determine whether Glendale�s agreements allow netting. A review of Cerritos� participation in the agreements is also being conducted.
Coordinating Committee Action at its Meeting on March 18
Project Manager�s Actions Since Last Project Director�s Report of March 15
With consultation and agreement from Project Participants, the following actions have been taken:
Key Milestones and Anticipated Significant Activities For Next 30 Days
Power Supply Capital Projects
� SCADA/EMS
Two Remote Terminal Units (RTU) have been installed at the new Hollywood Way Station by ABB. One RTU serves the 34.5 kV side and the other serves the 12 kV side of the station. Testing on both 12 kV and 34.5 kV RTU�s has been completed by ABB and BWP. Development of the new Hollywood Way Station displays, annunciator display, and RTU database has been completed. Testing on the 12 kV RTU is nearly complete. The first feeder carrying load transferred from the old Hollywood Way Station has been energized and tested. The transformer tap changer indication has been tested.
Because feeders from the old Hollywood Way Distributing Station will be transferred to the new station one at a time, the Scipar SCADA must be kept operational until June 30. . Telvent has delayed delivery of the Emergency Back-Up Server until April 19. Finalization of advanced application software and network communications with selected users will then follow.
The OATI Scheduling and Transaction Management System (STMS) software acceptance testing is still in progress. During March, automatic generation control of Lake 1, using the Telvent ITS software driven area control error signals derived from the OATI scheduling software, was successfully tested. Net interchange with LADWP was held to within 1 MW for several hours.
An initial meeting was held with LADWP to implement an Inter-Control Center Communications Protocol (ICCP) data link between BWP�s Telvent SCADA/Energy Management System (EMS) and their Energy Control Center. Real-time system load, generation, and reserves will be provided.
� Telecom
Engineering provided a proposal to Media Net for fiber optic service connecting Dakota Digital, 900 W. Alameda Ave., to the City of Los Angeles, LADWP Receiving Station �E� in North Hollywood.
Engineering provided a proposal to Disney to connect the following facilities:
Engineering provided a proposal to the City IT Department for fiber optic service connecting the North West Library to City Hall through SCADA.
Engineering released a job order to the Operations Section to provide an alternate link for Onfiber to connect Qwest Cyber Center to the Magnolia Basement. This job is related to the Hollywood Way relocation project.
Field personnel completed a fiber optic job to reroute the following Disney fiber optic links, going to the City of Glendale through the Flower Station:
Engineering released a job order to the Operations Section to disconnect the following Disney facilities:
Field personnel completed a fiber optic job for additional fiber strands to connect Warner Brother�s Building 157 to the Pinnacle Building, 3400 W. Olive Ave.
The status of Burbank Water and Power�s Administration Building Phase III � Interior Remodel remains on hold pending design changes, plan revisions and final approval.
Construction work for extending the ducts and manholes along Hollywood Way from the Warner Ranch Gate to Oak St., along Oak St. to California St., along California St. from Oak St. to Alameda Ave., and along Avon St. from Oak St. to the alley north of Alameda is complete. Perry C. Thomas, the private contractor for the Phase-2 underground ductwork, started construction on October 27 and completed all work except some final paving. The cable is on order and is expected to be delivered in the next two weeks.
Since July 1, 2003, a total of one hundred forty-five replacements/installations have been issued to the field, with nine replacements issued in March. Ninety-one poles have been replaced in this fiscal year. Construction of a thirty-pole line rebuild was started in March in the area between Clybourn and Pass Aves. south of National Ave.
Since July 1, 2003, sixteen pad mounted customer stations have been engineered, two of which was engineered in March. Since July, there have been ten pad mounted customer stations issued to the field and twelve pad mounted customer stations have been energized.
Primary service for the second phase of John Burroughs High School has been energized.
Since July 1, 2003, four series circuit conversions to low voltage have been completed and twenty-one new streetlights have been installed. Three streetlight improvement and undergrounding projects have been issued and two have been completed. The design for the second phase of the Magnolia Boulevard Project between Pass Ave. and Buena Vista St. has been completed. The BWP Board awarded the bid for the substructure work to Steiny and Company, Inc. on April 1, 2004.
BWP staff is participating in a Caltrans meeting to lengthen the Alameda, Hollywood Way and Pass Ave. bridges over SR-134, and developing cost estimates for Phase 2 of this project. Phase 1, which includes construction of the new Hollywood Way Substation and a transfer of load, is sixty percent complete. Construction of the new off-ramp was completed on June 30, 2003. The new Hollywood Way Station was completed and energized on March 1, and the remaining testing was completed by March 8. The dedication ceremony took place on March 30 and the load transfers are in progress and expected to be completed by May 21. By June 30, 2004 most of the 34,500 volt system will be reconfigured to connect four or five lines from the Capon Switching Station.
The Southern California Public Power Authority (SCPPA) awarded a contract to ABB Inc. to design/build the Gas Insulated Switchgear (GIS) expansion at the Olive Switching Station. This will connect the Magnolia Power Plant to the Olive Switching Station. ABB had two design review meetings with staff and submitted the design for Chief Building Officer (CBO) approval in the first week of February 2004. The construction started at the end of March as scheduled. Most of the equipment is on order or in manufacturing stage, and should be delivered by July 31. All work should be completed by November 2004.
Bock Co. is installing a new underground duct system in the BWP Yard to underground two 69,000 volt overhead lines as a part of BWP�s overall plan to improve and modernize the BWP generating site. The duct/manhole work is approximately ninety-five percent complete and the remaining five percent near the Olive Switching Station is still in progress. Both riser poles north of the Magnolia Bridge are completed along with cables to the first manholes at the northeast corner of the BWP Yard. This work is expected to be completed before MPP goes on-line.
BWP staff has started work on the Olive Switching Station retrofit by upgrading circuit breakers, busses and other equipment. This upgrade is needed for the Magnolia Power Project. Almost thirty percent of the work is completed.
A total of 1,418 remote meters have been installed; 768 were requested by the Customer Service Division, and 650 were meter change outs performed by the Line Crews or Test Shop.
CIS Project Overview:
Testing & Documentation Sign-Off:
Mock Go-Live Weekends:
Bill Print:
Reports:
Credit Cards:
Customer Access To Account Information:
End Users:
Go-Live:
Legislative Update:
Refer to the attached legislative reports.
RED:RAC:FCF:JWL:GLS:JLF H:APRIL W&E OPERATIONS REPORT
Attachments
|