|
Council Agenda - City of BurbankTuesday, March 30, 2004Agenda Item - 9 |
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
WATER UPDATE
Water Quality
Financial and Operations Update0
( ) Unfavorable
Environmental Protection Agency (EPA)
Capital Projects
Legislative Update
ELECTRIC UPDATE
Electric Reliability
The following table shows the systemwide reliability statistics through February 2004 for Fiscal Year 2003-04 as compared to Fiscal Year 2002-03:
Financial and Operations Update
Local Generation Operations Update
Unit Status
February 2004 Unit Data
Power Supply
BWP staff attended a public meeting with Commissioner Wood on January 16th regarding implementation of the SoCalGas Comprehensive Settlement Agreement (CSA). The goal of the CSA is to restructure the way gas transportation is handled on the SoCalGas systems. BWP staff worked on a letter to the California Public Utility Commission urging them not to adopt the implementation of the settlement. Letters were prepared by and sent out by Mayor Murphy and BWP�s General Manager to the Commissioners explaining how the proposed settlement would negatively impact the Magnolia Power Project. BWP�s Legislative Analyst worked with other Magnolia Power Project participants to encourage them to send similar supporting letters.
Due to the intensive lobbying efforts, an Alternative Decision, which supports BWP position was prepared by Commissioner Lynch. Although the CPUC was scheduled to vote on this issue on February 25th, however, this item was deferred to the meeting in March. Meanwhile, Commisioner Brown has revised the Draft Administrative Law Judge (ALJ) Decision by Judge DeUlloa. This revised draft is currently reviewed by staff. BWP staff is hoping that the Lynch Alternative will be adopted by the full Commission in March abandoning the Comprehensive Settlement.
Magnolia Power Project (MPP)
The items in this report are provided as a general overview of the status of the Project. These items are discussed in considerable detail among the Project Participants at the Project Coordination Meeting each Friday and at Coordinating Committee meetings.
Safety
Through February, Kvaerner has worked 119,947 man-hours with no lost time cases and two recordable cases.
Budget
Refer to the attachment for detailed information on actual expenditures.
Schedule
The project remains on schedule for a commercial operation date of May 25, 2005. Refer to the attachment for detailed information on Project milestones.
Finance
No Project A refinancing is planned at this time.
CEC Compliance
Excavation monitoring continues pursuant to Conditions of Certification. Monthly reports are being made as required by the CEC. No violations of conditions have occurred.
Engineering, Procurement and Construction Activities since last Project Director�s Report of February 16, 2004.
Transmission
Facilities Agreement. Navigant has persuaded LA to agree to the correct percentages for the Project�s contribution to short circuit duty. The Agreement will require a provision that allows Magnolia to operate whether or not the work on the LA system is performed.
Transmission Study Project. Magnolia participants are being polled to determine their level of interest in the Transmission Study. Personal Services Agreements will outline scopes of service on legal and regulatory issues associated with an interconnection with Southern California Edison.
Scheduled Services. Glendale will need two reactors at Western to fulfill its obligations for scheduled services. Delivery time for reactors is about 4 months for standard orders. Don Allen is reviewing the primary agreements to determine whether Glendale�s agreements allow netting. A review of Cerritos� participation in the agreements is also being conducted.
Coordinating Committee Action at its Meeting on February 19, 2004
Project Manager�s (Project Director�s) Actions Since Last Project Director�s Report of February 16
With consultation and agreement from Project Participants, the following actions have been taken:
Key Milestones and Anticipated Significant Activities For Next 30 Days
Power Supply Capital Projects
Two Remote Terminal Units (RTU) have been installed at the new Hollywood Way station. One RTU serves the 34.5 kV side and the other for the 12 kV side of the station. Testing on the 34.5 kV RTU has been completed by ABB and BWP. Testing on the 12 kV one is about 75 percent complete. Development of the new Hollywood Way Station displays, annunciator display, and RTU data base has been completed.
Because of the need to transfer feeders from the old Hollywood Way Distributing Station to the new one, the Scipar SCADA must be kept operational until June 30.
Delivery of the Emergency Back-up Server has been set for early March. Finalization of advanced application software and network communications with selected users will then begin.
The Scheduling and Transaction Management System (STMS) software is being implemented. The web-based OATI software, and integration with the Telvent SCADA system has been completed. On-site testing has begun and software acceptance testing has started with completion and energy scheduling on an operational basis using STMS expected by mid-March.
Engineering provided a proposal to MediaNet for fiber optic service connecting Disney CORE 914 Victory Blvd. to City of Los Angeles, LADWP Receiving Station �E� in North Hollywood.
Engineering provided a proposal to Disney to connect Team Disney, Disney Channel and Disney Tower facilities redundantly to BWP fiber optic ring.
Engineering provided a proposal to Warner Brothers to connect Warner Building 157 redundantly to all their other facilities in the City of Burbank.
Field personnel completed a fiber optic job for the new Hollywood Way MUX connection from old Hollywood Way to Alameda Station.
The status of Burbank Water and Power�s Administration Building remodel remains on hold pending design changes, plan revisions and final approval.
Rerouting of the 34.5 kV Burbank-San Jose line is complete.
Construction work for extending the ducts and manholes along Hollywood Way from the Warner Ranch Gate to Oak Street, along Oak Street to California Street, along California Street from Oak Street to Alameda Avenue and also along Avon Street from Oak Street to the alley north of Alameda is complete. Perry C. Thomas, the private contractor for Phase-2 underground ductwork, started construction on October 27 and completed all work except some final paving. The cable is on order and is expected to be delivered in the next 2 to 4 weeks.
Since July 1, 2003, a total of one hundred thirty six replacements/installations have been issued to the field, with thirty four replacements issued in February. Sixty three poles have been replaced in this fiscal year. Construction of a 22-pole line rebuild was started in January in the area between Lincoln and Keystone Streets north of Kenneth Road.
Since July 1, 2003, fourteen pad mounted customer stations have been engineered, two of which was engineered in February. Since July, there have been eight pad mounted customer stations issued to the field and ten pad mounted customer stations have been energized.
Primary service with two pad mounted switches for Senior Aerospace were energized in January.
Underground work to provide the new St. Joseph Providence Hospital building and the Burbank Medical Plaza with service availability from two different 12 kV feeders each coming from a different distributing station has been completed. Service was energized in February.
The Bock Company has completed a primary underground portion of work providing service to the Administration Building water pump.
Since July 1, 2003, three series circuit conversions to low voltage have been completed and twenty one new streetlights have been installed. Three streetlight improvement and undergrounding projects have been issued and one has been completed. The design for the second phase of the Magnolia Boulevard Project between Pass Avenue and Buena Vista Street has been completed. The bid process is in progress.
BWP staff is participating in a Caltrans meeting to lengthen the Alameda, Hollywood Way and Pass Ave. bridges over SR-134, and developing cost estimates for Phase 2 of this project. Phase 1, which includes construction of the new Hollywood Way Substation and a transfer of load, is sixty percent complete. Construction of the new off-ramp was completed on June 30, 2003. New Hollywood Way Station is almost completed and ready to be energized. The substation will be energized on March 1 and the remaining testing would be completed by March 8. The dedication ceremony of the substation is scheduled on March 30 at 10 a.m. and load transfers immediately after that to complete it by May 21. By June 30, 2004 most of the 34,500 volt system will be reconfigured to connect four or five lines from the Capon Switching Station.
SCPPA awarded a contract to ABB Inc. to design/build the Gas Insulated Switchgear (GIS) expansion at the Olive Switching Station. This will connect the Magnolia Power Plant to the Olive Switching Station. ABB has two design review meetings with staff and submitted the design for Chief Building Officer (CBO) approval in the first week of February 2004. The construction is expected to start by the end of March or early April. Most of the equipment is on order, or in manufacturing stage and should be delivered by July 31 and all work completed by November 2004.
Bock Co. is installing a new underground duct system in the BWP Yard to underground two 69,000 volt overhead lines as a part of BWP�s overall plan to improve and modernize the BWP generating site. The duct /manhole work is approximately 80 percent complete and only the last segment near Olive Switching Station is still in progress. Both riser poles north of Magnolia Bridge are completed along with cables to the first manholes at the north east corner of BWP Yard. This work is expected to be completed before MPP goes on-line.
BWP staff has started work on the Olive Switching Station retrofit by upgrading circuit breakers, busses and other equipment. This upgrade is needed for the Magnolia Power Project.
A total of 1,175 remote meters have been installed; 687 were requested by the Customer Service Division, and 488 were meter change outs by the Line Crews or Test Shop.
Legislative Update:
Refer to the attached legislative reports.
RED:RAC:FCF:JWL:GLS:JLF H:MARCH W&E OPERATIONS REPORT rev 2
Attachments
|