WATER UPDATE
Water Quality
Financial and Operations Update
-
Potable water sales for January were 729,073 billing units. This was 1% lower
than the budgeted sales. Revenue for January was
$1,235,274.
-
Reclaimed water sales for January were 12,941 billing units. Revenue for
January was $16,905, not including Power Plant sales.
-
The Water Cost Adjustment Charge (WCAC) account had a balance of $1,466,965 as
of January 31, 2004.
-
Fiscal Year 2002-03 Year-To-Date preliminary Water Fund Financial Results as
of January 31, 2004:
Capital Projects
-
Replacement of interior joints at Reservoir No. 2 is complete. The reservoir
has been cleaned, disinfected, and is leak tested. As a result of the leak
testing, additional work by the contractor is required. Localized problems
with the bonding of the lining are being investigated and resolved. Additional
leak testing took place in January. Resolution of the leakage is being pursued
with the contractor. The reservoir will be placed back in service by March
2004.
-
The project to install 1,100 L.F. of
12-inch water main in Buena Vista St. from Alameda Ave. to Olive Ave. was
completed with the abandonment of the old main in January 2004.
-
Construction of 140 L.F. of a new 8-inch
main was completed on Palm Ave., west of 6th St. The new main is
now in service.
-
Construction of a new 12-inch main on
Verdugo Ave. between Third St. and South San Fernando Blvd. began in January.
This construction is related to the Senior Artist Colony project and scheduled
to be completed by February 2004.
Legislative Update
ELECTRIC UPDATE
Electric Reliability
-
There were no outages during January 2004.
As of January 2004, the systemwide average remains at 0.1965 outages per year,
compared with an industry average of 1.2 outages per year. As of January 2004,
the average service availability is 99.9955%, exceeding the City goal of
99.99%. The average outage length remains 68 minutes, compared with an
industry average of 80 minutes.
The following table shows the systemwide
reliability statistics through January 2004 for Fiscal Year 2003-04 as compared
to Fiscal Year 2002-03:
Reliability Measure |
Fiscal Year 2002-03 |
Fiscal Year 2003-04, Through Jan. 31 |
Average
Outages Per Year |
0.16634 |
0.1965 |
Average Outage
Duration |
91.75 minutes |
68.21
minutes |
Average
Service Availability |
99.9971% |
99.9955% |
Financial and Operations Update
-
MWh sales of 86,874 for January were above the budgeted amount of 85,046.
Year-to-date MWh sales remain above budget due to warmer average temperatures
during the summer months and cooler average temperatures during the winter
months.
-
Wholesale gross margins were above budget for the month of January due to
BWP�s ability to utilize its assets to increase sales in the wholesale market.
-
Fiscal Year 2003-04 year-to-date preliminary Power Financial Results as of
January 31, 2004:
Local Generation Operations UPdate
Unit Status
-
Olive 1 is down for its annual boiler inspection. This unit will be back in
hot-standby on March 8.
-
Olive 2 is on-line for system tuning, boiler feed pump and the Relative
Accuracy Test Audit (RATA) testing. The testing was completed on February 9th
and this unit is available for normal service.
-
Olive 3 has been decommissioned as of December 31, 2003 per the SCAQMD permit
requirements of January 31st.
-
Olive 4 has been decommissioned as of December 31, 2003 per the SCAQMD permit
requirements.
-
Magnolia 5 has been decommissioned as of December 31, 2003 per the SCAQMD
permit requirements.
-
Lake One is available for service.
-
The Micro-Turbine Project has been awarded to SCS Energy. The project is now
in the planning stage. The Micro-Turbines will not be running until the spring
of 2004.
-
Hydro Energy Production for January was 69,400 kWh compared to the 58,000 kWh
goal. Year-to-date kWh production of 507,300 was above the kWh goal of
408,000.
January 2004
Unit Data
Unit |
Availability |
Operating Hours |
MW Net |
NOx, lbs. |
M-5 |
0% |
0 |
-6 |
- |
L-1 |
100% |
85 |
2629 |
546 |
O-1 |
100% |
0 |
-146 |
81.96 |
O-2 |
55% |
90 |
893 |
894.67 |
O-3 |
0% |
0 |
-33 |
- |
O-4 |
0% |
0 |
-13.1 |
- |
Power Supply
BWP staff attended a public meeting with Commissioner Wood on January 16th
regarding implementation of the SoCalGas Comprehensive Settlement Agreement
(CSA). This will restructure the way gas transportation is handled on the
SoCalGas systems. BWP staff has been working on a letter to the California
Public Utility Commission urging them not to adopt the implementation of the
settlement which is scheduled to be voted on at the February 11, 2004 meeting.
Letters have been prepared by and sent out by Mayor Murphy and BWP�s General
Manager to the Commissioners explaining how the proposed settlement would
negatively impact the Magnolia Power Project. BWP�s Legislative Analyst is
working with other Magnolia Power Project participants to encourage them to send
similar supporting letters.
The February 11, 2004 vote did not take place. With the outpouring of
opposition to the CSA, Commissioner Kennedy asked that the CSA be held over
until the next meeting on February 26, 2004.
Magnolia Power Project (MPP)
The items in this report are provided as a general overview of the status of the
Project. These items are discussed in considerable detail among the Project
Participants at the Project Coordination Meeting each Friday, and at
Coordinating Committee meetings.
Budget
Refer to the attachment for detailed information on actual expenditures.
Schedule
The project remains on schedule for a commercial operation date of May 25, 2005.
Refer to the attachment for detailed information on Project milestones.
Finance
No Project A refinancing is planned at this time.
CEC Compliance
Excavation monitoring continues pursuant to the Conditions of Certification.
Monthly reports are being made as required by the CEC. No violations of
conditions have occurred.
Engineering, Procurement and Construction Activities since last Project
Director�s Report of January 12, 2004
January 29: |
Completed pedestal framing for steam turbine
generator |
February 5: |
Completed underground fire protection piping |
February 6: |
Awarded heavy haul contract |
February 6: |
Completed installation of turbine pedestal for
combustion turbine generator |
February 13: |
Completed engineering for 69kV ductbank
|
Transmission
It appears
that LADWP has persuaded the City attorneys in Los Angeles to accept the Letter
Agreement route rather than the route of obtaining approval from the Board of
Water and Power Commissioners. LADWP staff raised the issue of whether the
Facilities Agreement should reflect the impacts of other LADWP stations besides
Receiving Station E. BWP staff has taken the position that �a deal�s a deal� and
that the Facilities Agreement should continue to reflect only the impacts on
Receiving Station E.
The management teams of
Burbank and Glendale have reviewed the economic
feasibility of scheduled service, and have concluded that they can offer
significant savings to the ISO participants in comparison to the Open Access
Transmission Tariff. The Magnolia ISO participants have been informed of the
deal points and the proposed savings that could be offered.
Physical ties involving
Edison continue to be actively pursued. BWP
staff met informally with Don Allen and have reached a preliminary conclusion
that the physical option, while likely to be contested, is legally feasible.
Staff is continuing to review LADWP�s proposal
for operational arrangements with LADWP that would provide opportunities to
deliver Project output to the ISO under an integrated facilities agreement.
At the December 18 Coordinating Committee
meeting, a presentation was made on the various transmission issues and there
was preliminary agreement to take steps to form a separate study group to pursue
physical transmission alternatives.
Coordinating Committee Action at its Meeting on January 15, 2004
No action items were approved.
Project Manager�s (Project Director�s) Actions Since Last Project
Director�s Report of January 12
With consultation and agreement from
Project Participants, the following actions have been taken:
-
Authorized
$130,050 for Kvaerner to provide the required Construction Mitigation
Management (CMM) assistance services for the Project from December 2003
through December 2004.
-
Authorized
$53,411 for Kvaerner to provide custom paint colors for the balance of plant
equipment, as required by the CEC license.
-
Authorized
$423,573 for Kvaerner to increase the size of the ductbank to accommodate
additional conductors (changing from six, 1500 MCM conductors to nine, 1250
MCM conductors per transformer).
-
Authorized
$120,367 for Kvaerner to provide labor and materials to paint the Combustion
Turbine Generator to comply with the California Energy Commission (CEC)
license.
-
Authorized
$133,870 for ABB to increase their scope of work to include extending the
power duct banks, extending the control cable trench, relocating the control
enclosure to a new location, extending the control duct package, and providing
engineering of these items.
-
Authorized
$31,988 for GE to modify the generator control panels to match the ABB
synchronizing voltage transformers (VT) that are being provided for the high
voltage switchyard.
-
Authorized
$138,244 deducted from Kvaerner to delete the electrical fire pump and jockey
pump taking water from the reclaimed water storage tank, because the City
water system contains adequate pressure and flow to satisfy code requirements.
-
Authorized $70,905 for Kvaerner to add vibration sensors to protect the boiler
feedwater pumps.
-
Renewed
Professional Service Agreement for on-going consulting services with Jennifer
Wu.
Key Milestones and Anticipated Significant Activities For Next 30 Days
February 20: |
Install potable water system |
February 27: |
Complete blowdown tank foundation for heat
recovery steam generator |
February 27: |
Award contract for turbine bypass valves |
March 4: |
Complete cooling tower basin |
March 12: |
Complete system one-lines and schematics for
zero liquid discharge system |
Power Supply Capital Projects
One Remote
Terminal Unit (RTU) remains to be installed and tested for the new Hollywood Way
Station. This RTU is being designed and installed by ABB, Inc and is expected to
be completed by early March. Development of the new Hollywood Way Station
displays, annunciator display, and RTU data base has been completed.
Because of
the need to transfer feeders from the old Hollywood Way Distributing Station to
the new one, the Scipar SCADA must be kept operational until June 30.
Delivery of
the Emergency Back-up Server has been set for early March. Finalization of
advanced application software and network communications with selected users
will then begin.
The
Scheduling and Transaction Management System (STMS) software is being
implemented. The web-based OATI software, and integration with the Telvent SCADA
system is progressing on schedule and estimated to be completed by March 2004.
On-site testing has begun and software acceptance testing has started with
completion expected at the end of February.
Engineering
provided a proposal to MediaNet for fiber optic service connecting Modern Video
Film at 4411 W. Olive Avenue to the City of Los Angeles, LADWP Receiving Station
�E� in North Hollywood.
Engineering
released a job order to the Operations Section to install fiber cable and
provide a second backbone through the Media District. This is in preparation for
the relocation of the fiber hub from the old Hollywood Way control room to the
new Telecom Room at the Hollywood Way Substation. This will allow minimum
impact on existing fiber customers.
Engineering
released, and field operations personnel completed a fiber optic job for �The
Switch TV�, to connect an additional two (2) fiber strands from NBC
Studios to the City of Los Angeles� LADWP Receiving Station �E� in North
Hollywood. This is a test connection between LADWP and BWP fiber networks to
market a new service. The link provides a direct connection cross-country
between NBC Burbank and NBC New York for both the Tonight Show with Jay Leno and
Access Hollywood.
Field personnel
completed a fiber optic job for Ascent Media to connect their facility at 2901
W. Alameda Avenue to the Qwest Cyber Center 3015 Winona Avenue.
Field personnel completed a fiber job to disconnect two (2) Warner fiber links:
-
WEA 111 N. Hollywood Way to West Olive Plaza 3601 W. Olive Avenue
-
Warner
Building 157 to Warner Empire 1935 Buena Vista Street.
The status of Burbank Water
and Power�s
Administration
Building
remodel remains on hold pending design changes, plan revisions and final
approval.
Rerouting of the 34.5 kV Burbank-San Jose line
is complete.
Construction work for extending the ducts and
manholes along Hollywood Way from the Warner Ranch Gate to Oak Street, along Oak
Street to California Street, along California Street from Oak Street to Alameda
Avenue and also along Avon Street from Oak Street to the alley north of Alameda
is complete. Perry C. Thomas, the private contractor for Phase-2 underground
ductwork, started construction on October 27 and completed the installation of
all manholes. They are currently working on the installation of a duct system on
Oak Street near Catalina Street towards
Buena Vista
and California Street. This work is approximately thirty percent completed.
Since July 1, 2003, a total of one hundred two
pole replacements/installations have been issued to the field, with nine
replacements issued in January. Sixty poles have been replaced in this fiscal
year. Construction of a 22-pole line rebuild was started in January in the area
between Lincoln and Keystone Streets north of Kenneth Road.
Since July 1, 2003, twelve pad mounted
customer stations have been engineered, one of which was engineered in January.
Since July, there have been seven pad mounted customer stations issued to the
field and eight pad mounted customer stations have been energized.
Primary service with two pad mounted switches
for Senior Aerospace were energized in January.
Underground work to provide the new St. Joseph
Providence
Hospital building and the Burbank
Medical Plaza with service availability
from two different 12 kV feeders each coming from a different distributing
station has been completed.
Since July 1, 2003, three series circuit
conversions to low voltage have been completed and twenty new streetlights have
been installed. Three streetlight improvement and undergrounding projects have
been issued and one has been completed. The second phase of the Magnolia
Boulevard Project between Pass Avenue and Buena Vista Street is being
engineered.
BWP staff is participating in a Caltrans meeting
to lengthen the Alameda, Hollywood Way and Pass Ave. bridges over SR-134, and
developing cost estimates for Phase 2 of this project. Phase 1, which includes
construction of the new Hollywood Way Substation and a transfer of load, is
sixty percent complete. Construction of the new off-ramp was completed on June
30, 2003. BWP staff expects the new Hollywood Way Station to be completed by
April 2004. By June 30, 2004 most of the 34,500 volt system will be reconfigured
to connect four or five lines from the Capon Switching Station.
SCPPA awarded a contract to ABB Inc. to
design/build the Gas Insulated Switchgear (GIS) expansion at the Olive Switching
Station. This will connect the Magnolia Power Plant to the Olive Switching
Station. The preliminary design is in process and construction is expected to be
completed by November 2004.
Bock Co. is installing a new underground duct
system in the BWP Yard to underground two 69,000 volt overhead lines as a part
of BWP�s overall plan to improve and modernize the BWP generating site.
BWP staff has started work on the Olive Switching Station retrofit by upgrading
circuit breakers, busses and other equipment. This upgrade is needed for the
Magnolia Power Project.
A total of 1,013 remote meters have been installed; 609 were requested by the
Customer Service Division, and 404 were meter change outs by the Line Crews or
Test Shop.
The Customer Service Division is implementing the Indus Banner billing system to
enhance customer bills. The system is expected to go live in June 2004.
Project Overview:
-
78 Deliverables, 62 completed, 79% complete.
-
Indus implementation budget, $2,261,012, expended $1,525,416,or 67%
-
Total project
budget, $4,678,300, expended $3,296,806, or 70%.
-
Supplemental technical implementation budget, $1,000,000, expended $128,544,
or 13%.
-
On target for
go-live by June 2004.
System Testing:
-
All eighty-five issues discovered during system tests have been resolved and
closed.
-
User Acceptance Testing (UAT) began January 7, 2004, with a kick-off meeting
to introduce the concept and process of UAT to the core team and an expanded
group of thirty-two testers from various departments and work groups who
participated in the UAT process.
-
UAT is a disciplined comprehensive process of testing and verifying our
business processes to ensure that the Banner application, set up, and
production environment work together correctly and that the system�s
accessibility and functionality meet functionality. The UAT plan is attached
for your information.
-
Using both the core team and the expanded group of testers in the UAT was very
successful. Not only did the core team need the extra hands, but it allowed
the testers and high-level system users to get exposure to the new system, and
gain familiarity prior to go-live.
-
During the UAT, actual legacy transactions were captured on three separate
dates during the month of January. These transactions were then duplicated in
Banner, processed in Banner, and then the output verified and balanced against
Legacy outputs.
-
To date, UAT testing has resulted in ninety issues. Forty-nine are now closed.
End User Training:
-
All Departments were asked to submit names of those staff members who will
need to access the Banner system. A total of ninety-five names were submitted.
Thirty-two testers have already been trained through the UAT process. The
remaining sixty-three will be trained in small groups by their representative
on the core team.
-
Training began in February and will continue through go-live as needed.
Conversion:
-
A full data conversion was completed in January in preparation for the UAT.
-
Conversion issues continue to arise as expected. Most are solved by the Indus
conversion specialists, but some problems are better solved by continuing to
clean the Legacy data.
-
Another full conversion was completed during the first week of February to
incorporate fixes performed during January.
-
One piece of good news is that the financials balanced within pennies.
Mock Go-Live
Weekends:
-
Staff has decided
to conduct two mock go-live weekends to identify any bugs or holes in the
go-live plan, to refine our timing estimates for go-live activities, and to
ensure everyone is familiar with the process and their role.
-
Mock go-lives are
scheduled for February 28-29 and March 20-21.
-
A detailed go-live plan is being prepared.
Bill Print:
-
Staff has printed residential bills successfully, although several fields of
information were not accurate.
-
Group 1, our bill print vendor, has dropped code to fix several of the
identified bill print problems. Staff is waiting for the second fix.
-
Large customer bills have not been produced yet.
-
The format for totalized bills has not been finalized.
-
With the legacy system, our OCE printer was programmed to handle the bill
formatting. With the Banner system, Group 1 can handle bill formatting.
Banner does not produce collection notices as part of the batch bill run but
they�re really not a bill, per se, merely a reminder or notice to the customer
about a bill already produced. The only problem this creates for us is that
OCE may still have to do some formatting for the notices, meaning programming
and unexpected expense. The Indus project manager is working on this problem.
Technical Issues:
-
The last two interfaces have been delivered, Itron and GL. All modifications
and interfaces are now being tested.
-
The BillGen database, complex billing engine for the Banner application, has
been updated again, to version 8.7.88. This version solves several problems
discovered during system testing.
-
Oracle databases have been upgraded to Oracle 9i.
-
IT has loaded updated Oracle drivers on the Integrated Voice Response (IVR)
server to allow our IVR vendor to remotely install and test their portion of
programming required to interface with Banner.
-
IT spent significant time testing the backup/failover mechanism between the
production servers to the development servers to ensure there is no single
point of failure for the Banner systems.
-
The first batch process has been developed and was run in January. The batch
process is the nightly process that calculates and prints bills, posts
payments, updates files, and creates reports.
-
Indus and IT are working on a technical cut-over plan to transition support of
the system from Indus to IT.
-
IT has created most of the forty custom reports requested by system users,
which will be included in the nightly batch process and produced for user
review, testing, and verification.
-
IT is working to
ensure that all appropriate workstations are configured properly and Banner
icons are installed for all system users.
Customer Issues
-
To make the conversion and go-live weekend cleaner and less complicated, staff
has decided to true up all level pay customers in February, before going-live,
instead of the regular true up month, October. Level pay customers will
receive a letter with their February bill informing them that either a credit
or debit will be displayed on the bill, which closes out their level pay
status for the time being. Customers will be placed back on the program
automatically in April. In addition, customers were informed that Banner has a
different true up mechanism than Legacy. Rather than a lump sum credit or
debit in October, Banner will assess the customer�s situation after one year
and will automatically spread any lump sum, positive or negative, over the
following twelve months.
-
Staff is preparing to accept credit cards over the phone and internet at
go-live. Bank fees for credit cards can be a huge liability if larger
customers elect to pay their bill with a credit card. Billers are not allowed
to charge a convenience fee to cover the costs, however, a third-party
provider can. To minimize costs and place the cost of a service firmly with
the one that benefits from the service, the City has elected to use a
third-party provider rather than pay the bank fees as a cost of doing
business. The City Treasurer is working on an agreement with Official Payments
to be our third-party provider of this service and expects to request City
Council approval in early March. Official Payments uses an escalating fee
schedule to charge customers a convenience fee based on the amount of their
bill.
-
BillGen was recently added to the Banner suite of products. As such, it is not
fully integrated into the Banner application. One of the key issues is that
BillGen calculates the complex rates and sends them to Banner for handling and
bill print along with the rest of the Banner accounts. However, BillGen can
not pass the rate algorithms to Banner and therefore, those bills will only
display consumption data and amount due. Currently, the bills display the
actual formula used to calculate the amount due so the customer can double
check the figures. Indus does have a solution, Enerlink.net, which allows
BillGen customers access to detailed account information over the internet.
Although internet account access was originally planned for Phase II of the
CIS implementation, this glitch necessitates making the Enerlink.net
application available at go-live. Staff is currently working on where the
application will reside
-
Staff is still planning to implement the application, which will allow the
balance of customers to access their account information over the internet
before the end of the calendar year. This requires the purchase of a server,
which is being requested in the Fiscal Year 2004-05 budget.
Project Issues:
-
The decision has been made to minimize printing paper reports. Banner reports,
E-Dash reports (high level, summary information), and custom reports developed
by IT can all be accessed on line. Ideally, all reports will be accessible
from one portal. Indus and IT are working on the best solution, either through
E-Dash or Banner�s electronic work queue.
-
Staff is considering two options for handling intra-City accounts. The first
option requires setting up master accounts for each department and then
determining appropriate accounts and cost centers to be linked to the master
account. Each month, staff would get a report of the charges and manually post
payments to the accounts. The second option requires Indus to program these
transactions so that when the accounts are billed, the payments are posted and
the A/R is cleared. This would eliminate the need to manually enter payments
each month. Both options would be set up so the cash, expenses, and A/R would
automatically transfer to the appropriate funds when the payment posts. The
preliminary estimate for this work is thirty-two hours, or $5,728.
-
BillGen testing has been slow and still remains a concern. Staff may request
an additional week of on-site time for the BillGen programmer.
Financial Issues:
-
Indus has agreed that water and electric demand were, in fact, within the
original scope of work to be performed by Indus. This means that the charges
for those modifications will be paid by Indus. This equates to 439 hours, or
$78,000.
-
The following change orders impacting the budget have been agreed to:
Number |
Description/Benefit |
Hours/Cost Estimate |
CO1 |
Allows the ability to bill streetlight and UUT
as a percent of electric revenue. Allows cash for one GL to go to multiple
funds. |
34.5 hours - $61,755 |
CO2 |
Allows Power Factor percentage to be passed from
BillGen to Banner, printed on the bill, and stored on the consumption
history screen. |
45 hours - $8,055 |
CO3 |
Allows the ability to have school accounts
billed in BillGen according to contract. |
8 hours - $1,432 |
CO4 |
Modifies the bank draft data feed process to
accommodate Bank of America�s formatting |
6 hours - $1,074 |
CO5 |
Allows the ability to calculate and display
water demand appropriately for compound meters |
32 hours - $5,728 |
CO 6 |
Allows the ability to use same Banner high/low
logic for peak registers (KW) that Banner uses for non-peak registers. |
26 hours - $4,654 |
CO7 |
Allows the ability to print an OCR scan line on
collection letters |
10 hours - $1,790 |
Legislative Update:
Refer to the
attached legislative reports.
RED:RAC:FCF:JWL:GLS:JLF
H:FEBRUARY W&E OPERATIONS REPORT
Attachments
go
to the top