Council Agenda - City of Burbank

Tuesday, June 3, 2003

Agenda Item - 5


 

CITY OF BURBANK

PUBLIC WORKS DEPARTMENT

MEMORANDUM

 

DATE: June 3, 2003
TO: Mary J. Alvord, City Manager
FROM:

Bruce S. Feng, Public Works Director

Susan M. Georgino, Community Development Director

SUBJECT: CHANDLER BOULEVARD BIKEWAY PROJECT


PURPOSE:
 

The purpose of this report is to provide an update on the Chandler Boulevard Bikeway Project.

 

RECENT DEVELOPMENTS:

 

Removal of railroad tracks


In December 2002, the City entered
into an agreement with JDK Railroad Materials, LLC to demolish the tracks on the project site. This operation started in January and by the end of February all tracks were removed from the site. The rails were destined for recycling and the ties for re-use on another railroad in Ventura County, all at no cost to the City.

 

Authorization from Caltrans to proceed with bikeway construction


Also in December 2002,
staff submitted the required Federal documents along with the Bikeway plans, specifications, and estimates (PS&E) to Caltrans for their review and authorization.  This authorization is needed before the City can proceed with advertising for construction bids.

 

The review process typically takes 60 days to complete. However, in March, the Caltrans Environmental Division requested a Historic Property Survey Report and an Archaeological Survey Report to be performed on the right-of-way.

 

After conducting a site visit with City staff, Caltrans Environmental Division personnel determined that no historic cultural resources were present in the project area that might have been eligible for nomination to the National Register of Historic Places or to the California Register of Historic Places. Likewise, a cultural resources records search by the South Central Coastal Information Center indicated that no archaeological work was needed at this time. Staff was thus able to satisfy both of Caltran�s requests, and expects to receive PS&E approval in early June.

 

Fiber Optic installation agreement with MTA


For the last six months, at the request of MTA, City and MTA staff had been working to develop a reimbursement agreement for the design and construction of
a fiber optic conduit in the Bikeway project. The intent of this agreement was to prevent future disruption of the bikeway construction, or damage to the finished bikeway, if MTA decided to construct the conduit at a later date.

 

In March 2003, staff forwarded the cost estimate, along with the final version of the agreement, to MTA for signature. However, in April, MTA notified the City that they had decided to design and construct the fiber optic conduit with their own forces before the City starts the bikeway construction. Staff anticipates this will prevent several weeks, if not months, of additional delay in attempting to reach an agreement with MTA on the fiber optic design and construction issue.  MTA is expected to begin construction of the fiber optic conduit in July and complete it by October 2003.

 

Updated Project Schedule

 

Assuming Caltrans issues the Authorization to Proceed in early June 2003, the anticipated project schedule is as follows:

 

date

City schedule

mta schedule

June 2003

Authorization to Proceed with bidding from Caltrans

 

June 2003

Advertise for bids

 

July 2003

Bid opening and selection of contractor

Fiber optic

August 2003

Council award of Bikeway construction contract

construction

September 2003  

Pre-construction meeting

Notice to residents on construction schedule

 

October 2003

Begin bikeway construction

 

March 2004

Tree planting with community

 

April 2004

Complete construction

 

 

RECOMMENDATION:
 

Staff recommends that the City Council note and file this update.  Staff will continue to provide updates to Council to keep them informed of the project.

 

go to the top