WATER
UPDATE
Water
Quality
-
Water quality
during December met or exceeded State and Federal drinking water standards.
-
Water system tests
for total Chromium and Chromium 6 were taken on December 10. The results are
attached in table and chart format.
-
The Valley Pumping
Plant blend ratio for the month of December was 52.29% MWD to 47.71% BOU.
Financial
and Operations Update
-
Potable water sales
for December were 710,002 units. This was 3.21% lower than the budgeted
sales estimate. Revenue for December was $1,152,179.
-
Reclaimed water
sales for December were 7,370 billing units. Revenue for December was $9,443
not including Power Plant sales.
-
Fiscal Year 2002-03
Year-To-Date Water Fund Financial Results as of December 2002
$
in 000�s
(
) = unfavorable |
Year-To-Date
Actual |
Year-To-Date
Budget |
Variance |
CCF |
4,442,934 |
4,633,118 |
(190,184) |
Total
Revenues |
$
6,960 |
$
7,387 |
($427) |
Total
Operating Expenses |
5,911 |
6,709 |
798 |
Operating
Income/(Loss) |
$
1,049 |
$
678 |
$
371 |
-
The Water Cost
Adjustment Charge (WCAC) account had a balance of $1,107,319 at December 31,
2002.
-
The Burbank
Operable Unit produced 215.562 million gallons or 661.56 acre-feet of water.
The plant capacity factor for December was 53.65 %
-
The Lake Street GAC
Treatment Plant continues to be out-of-service except for routine monthly
operational maintenance and testing.
Environmental
Protection Agency (EPA)
-
BWP received a grant
to perform a Vulnerability Assessment from the EPA. Kennedy/Jenks was selected
as the Consultant. The Consultant and Water Division staff completed the site
visits and various rankings of facilities. We have received the
"Draft" report and are reviewing the document and developing
comments and recommendations.
-
The design work for
the modifications to the Liquid Phase Granulated Activated Carbon (LPGAC)
units was completed. Approvals were received from the DHS and Lockheed-Martin.
The BWP Board approved the necessary funding increase to the PSA with United
Water, Inc. EPA provided approval for fabrication of the necessary materials.
Approval for construction will follow after BWP submittal of the final design
report to the EPA.
Capital
Projects
-
The Water Division
completed work on a 12-inch pipeline in the intersection of Hollywood Way
and Thornton St. This work ties the developer-installed work on the A-1 Site
to the water system.
-
The Water Division
began construction work on the 16-inch main expansion of the Reclaimed Water
System on Chestnut and Mariposa. The project will provide reclaimed water
for the Chandler Bikeway and landscaping scheduled for construction in the
spring of 2003.
-
Replacement of
interior joint sealant at Reservoir No. 2 will begin in January 2003.
Legislative
Update
ELECTRIC
UPDATE
During
the first six-and-a-half months of FY 2002-03, there were 15 outages that
affected 6,920 customers, which equals a systemwide average of 0.1289 outages
per year compared with an industry average of 1.2 outages per year. The average
service availability is 99.996%, exceeding the City goal of 99.99%.
The
average outage length was 84 minutes, compared with an industry average of 80
minutes. Burbank fared much better than neighboring utilities in the recent
windstorm, in which 98.4% of our customers remained in service.
The
September 1 outage of 4 kV Feeder M-5 lasted 3 hours and 25 minutes due to phase
imbalance and a November 10 outage of the 12 kV Feeder SJ-10, which lasted 6
hours and 8 minutes, resulting from the failure of a padmount switch. We are
reviewing procedures and training with the goal of reducing outage response
times to below the industry average. Burbank fared much better than neighboring
utilities in the recent windstorm, in which 99% of BWP�s customers remained in
service.
The
following table shows the systemwide reliability statistics for FY 2001-02
compared to the first six-and-a-half months of FY 2002-03.
Reliability
Measure |
FY
2001-02 |
FY
2002-03,
July
1 to January 15 |
Average
Outages Per Year |
0.2564 |
0.1289 |
Average
Outage Duration |
57.93
minutes |
83.94
minutes |
Average
Service Availability |
99.9943% |
99.9961% |
Financial
and Operations Update
Amounts
in 000�s
(
) = unfavorable |
Year-To-Date
Actual |
Adopted
Budget |
Variance |
MWh |
554,157 |
577,112 |
(22,955) |
Total
Revenue |
$
100,393 |
$
83,001 |
$
17,392 |
Total
Operating Expenses(a) |
90,721 |
83,124 |
(
7,597) |
Operating
Income/(Loss) |
$
9,672 |
$
(123) |
$
9,795 |
|
|
|
|
Retail
Revenue |
$
68,114 |
$
73,203 |
$
(5,089) |
Wholesale
Revenue |
31,298 |
8,817 |
22,481 |
Other
Revenue(b) |
981 |
981 |
0 |
Total
Revenue |
$100,393 |
$83,001 |
$
17,392 |
(a)
Includes in-lieu
(b)
Transmission and telecom sales
MWh sales of 83,415
for December were below the budgeted amount of 86,080. Temperatures were
cooler than average with heating degree days at 345 versus a 30 year average
of 317. Year-to-date MWh sales remain below budget due to conservation efforts
and cooler than average temperatures in the summer months.
Wholesale gross
margins were above budget for the month of December, but trending down from
the summer ($1.2M to $.4M). Winter months generally produce less wholesale
sales due to a decrease demand in energy. Year-to-date wholesale gross margins
continue to be higher due to BWP�s ability to efficiently use utility assets
to increase sales in the wholesale market during the summer months.
Local
Generation Operations Update
Unit
Status
-
Magnolia 2 turbine
demolition completed.
-
Magnolia 3 is in
cold shutdown status.
-
Magnolia 4 is in
cold shutdown status.
-
Magnolia 5 is
available for service.
-
Olive 1 is off
line. Unit is in cold shutdown status.
-
Olive 2 is off
line. Unit is in cold shutdown status.
-
Olive 3 is
available for service.
-
Olive 4 is
available for service.
-
Lake One is
available for emergency use only. All that remains to make the Lake One
combustion turbine operational is successful operation of the unit�s NOx
reduction equipment, the SCR. Prior tests nearly passed. At high load
levels, the NOx levels exceeded the 5 parts per million standard by just a
fraction. As a result, BWP conducted a detailed evaluation of the complete
system finding numerous refinements to improve the performance. The
manufacturer of the catalyst is currently replacing the catalyst and
providing our staff training regarding the installation and handling of the
catalyst at no cost to BWP.
The
new catalyst is expected to arrive in early February. It will be installed
immediately. Tests will be scheduled as soon as possible and under the most
favorable conditions possible. The test results will be compiled and certified
by an independent testing company and sent to the SCAQMD. The SCAQMD staff
will then review the results. If the results are satisfactory a permit to
operate will be issued. This process can take nearly two months.
-
The Magnolia
Cooling Towers 1, 2, 3 and 4 have been demolished. The BWP Yard is being
cleared and fenced off for the Magnolia Power Project. All personnel lockers
have been moved out of the Magnolia plant change room. An 8-foot section of
main and bypass gas fuel lines were removed from the Magnolia 3 and 4
boilers.
-
The Olive Units 1
and 2 boilers were out of hot standby and cooled down on December 12. Olive
Unit 1 is being abated for asbestos in the areas needed for the NOx Retrofit
Project.
-
The Olive and
Magnolia Combustion Turbines were run due to loss of IPP power.
December
2002 Unit Data
Unit |
Availability |
Operating
Hours |
MWH
Net |
NOx,
lbs. |
M-3 |
0% |
0 |
0 |
0 |
M-4 |
0% |
0 |
0 |
0 |
M-5 |
100% |
2.117 |
38 |
- |
L-1 |
0% |
20.800 |
740 |
167.82 |
O-1 |
0% |
0 |
0 |
36.20 |
O-2 |
0% |
0 |
0 |
131.07 |
O-3 |
100% |
0.383 |
0 |
- |
O-4 |
100% |
0 |
0 |
- |
Power
Supply
-
Transmission and
Regional Transmission Organizations (RTOs)
The
filing date for comments on the Federal Energy Regulatory Commissions (FERC�s)
Notice of Proposed Rulemaking (NOPR), which deals with Standard Market Design
(SMD) for RTO�s, has been pushed back to January 2003. This is in response
to a "push-back" from various parts of the country, especially the
Northwest and Southeast. FERC�s SMD proposal has also been subject to
various congressional investigations. As well, FERC has recently approved the
formation of several new regional RTO�s whose market structure differs from
the blue print set forth in the NOPR. In view of the foregoing, it is not
known at this time whether or when SMD might be implemented.
-
FERC Data Requests
and Refund Calculation
FERC
has launched a 100 day investigation into the events that led to the price
run-ups in the natural gas and electricity markets in 2000 and 2001. Burbank
received an extensive data request from California Parties representing the
Attorney General and various State agencies. Considerable staff time was spent
during the month preparing BWP�s responses.
-
Restructuring of
Gas Industry in California
Implementation
of the Comprehensive Settlement by Southern California Gas Company (SoCalGas)
is still under suspension. It now appears that the California Public Utilities
Commission (CPUC) will be making a decision in mid-January regarding whether
the settlement should be implemented.
Capital
Projects
The
Remote Terminal Unit (RTU) modifications for the Victory Distributing Station
has been completed, as well as the annunciator change out at the Naomi
Distributing Station. Fieldwork is underway on RTU modifications for the
Naomi, McCambridge and Winona Distributing Stations. The RTU drawings for Town
Distributing Stations were issued. A Metso software engineer was on-site to
modify the Interchange Transaction Scheduling (ITS) software to correctly
reflect BWP�s energy scheduling practices. The tag designations requested by
the Dispatchers were successfully added as well as fast calculation software
to calculate and display percent line loading, power factor, etc. from
incoming data. The RTU installation at the Victory Distributing Station is
complete.
BWP
continues to link SCADA to the Distributed Control System (DCS) at the Olive
Power Plant and Lake Street. Work continued on the energy database and further
testing and development of the ITS/Automatic Generation Control (AGC)
software.
BWP
provided a proposal for fiber optic service to HeyAnita at 303 N. Glenoaks
Boulevard to the Qwest Cyber Center at 3015 Winona Avenue.
BWP
held a meeting with representatives from Verizon to begin discussions on
developing a partnership to provide existing customers and the City with
carrier level services.
-
BWP Administration
Building Remodel
Phase
III - Interior Building Remodel:
The
City Attorney's Office returned the bid package for Phase III of the Building
Remodel to BWP for final review and signatures. The architect, Fong Kutner and
Associates is still working at finalizing the construction drawings.
Engineering
for the Media District underground project, Bid Schedule No. 1133, has been
completed for extending the ducts and manholes along Hollywood Way from the
Warner Ranch Gate to Oak Street, along Oak Street to California Street, along
California Street from Oak Street to Alameda Avenue, and also along Avon
Street from Oak Street to the alley north of Alameda. Staff advertised for
bids in October and held the bid opening November 19. The bid award was
approved by the BWP Board on January 16, 2003.
Construction
of the new offramp (to allow construction of a new Hollywood Way Distributing
Station) will begin in January. Staff secured a Caltrans permit, and Pacific
Bell took care of their remaining lines.
Underground
ductwork has been completed near Hollywood Way and San Fernando, allowing an
overhead line to be rerouted along a less visible path.
Engineering
for Phase I of the DCSB has been completed; however, at this time there is
only approval to reroute the existing services and remove the poles.
Victory-Valley
No. 2 is energized, and the third 34,500-volt line position at Victory
Distributing Station is 50% completed.
Engineering
has been completed for replacing oil switches with SF6 switches at San Jose
Distributing Station. All fieldwork has been to prepare for taking an outage
and installing the switches in place.
Electric
service to Howard Business Park (Ontario Street) from the 34,500-volt system
has been completed.
Service
to Radio Shack has been rerouted to clear the old Police site.
In
addition to the identified major projects, 15 padmounted customer stations
have been engineered, and ten have been issued to the field.
Engineering
has been completed for the final phase of the Ben Mar Hills Project. Three
street light improvement and undergrounding projects have been issued to the
field.
Work
is underway to replace 1,200 residential electric meters with meters that can
be read remotely; 521 meters have been installed through January 15.